Site and Build Team Details

  • Site Code

  • Site Name

  • Conducted On

  • Prepared by

  • Location

Rigging Quality Assurance

Fall Arrest Systems

  • Is a Fall Arrest System Installed

  • Fall arrest system and Pegs have no obvious defects and are installed correctly (if required)
    1-3 Photos

  • X_FA1

  • FA2_Fall Arrest Certtification(s)
    Photos of the relvant certifications (Latrchway, Anchor Points, etc)

  • X_FA2

General Install

  • Photo of D shackles supporting DC & Fibre

  • X_Chain

  • Birdproofing is installed as required

  • X_Holes

  • All bolts attached to radios has anti-sieze grease applied before inserting bolt.
    4 to 6 photos showing grease applied to bolts before inserting

  • X_Grease

  • Photo of exisitng main earth at pole top

  • X_Earth Pole Top

  • Photo of exisitng main earth at pole base

  • X_Earth Pole Base

  • Overall Site View Photos (4 x Photos)

  • X_Site View

  • Photos to show RF Hazard Sign(s) installed

  • X-Signage

  • Is a shroud installed?

  • Photos to show shroud fixing with Tek Screws

  • X_Shroud

  • Has the Headframe been swapped?

  • Photos of the HeadFrame bolts to show Double nuts, direction of the bolt, etc)

  • X_HF1

  • Photos to show the Lightning Spike installation, including how the lightnng spike is secured

  • X_HF2

  • Have Lindaptors been installed?

  • Photos to show Lindapter installs including bolt directions, securing etc. As many photos as required to prove correct installation

  • X_Lin

  • Are New Chains installed inside pole?

  • Photos to show chains secured at top of pole

  • X_Chain Top

  • Photos to show chains secured at base of bale

  • X_Chain Base

Antenna Installs

  • Is S1 Installed

  • S1 wide view
    1 Photos
    Wide view of sector showing radios and antennas

  • X_S1

  • S1 bearing photo
    1-2 Photos
    Photo from top or side of antenna showing field of view (bearing)

  • X_S1 Azi

  • S1 Antenna brackets
    2 Photos
    Installation of antenna brackets

  • X_S1_2

  • Photo of S1 Antenna, Antenna label(s)
    2-4 Photos
    Photo of antenna and antenna label clearly showing antenna serial number

  • X_S1 Ant

  • Photo of S1 Antenna Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S1 Ant - M-Tilt

  • S1 NR Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S1 NR M-Roll

  • S1 - Sector information marked on antenna
    1 Photo
    Sector, Mechanical Tilt, Electrical Tilt, Azimuth and Height is marked

  • X_S1 Ant Info

  • S1 - ALD (RET) cable
    1-2 Photos
    Cable routed and connected correctly between the antenna and the High Band Radio 4499 B1+B3

  • X_S1 ALD

  • S1 - 3G/4G Antenna have correct Sector Label and Hazard Sticker
    1-2 Photos

  • X_S1 Ant Info 2

  • Has Air Equipment been installed on S1

  • Photo - AIR has been grounded with the double lug ground cable and lug screws have been tightened.

  • X_S1_Air1

  • Photo - AIR ground cable at grounding point has been terminated with the correct lug, correctly crimped and earth bonding paste used.

  • X_S1_Air2

  • Photo - Protective covers, dust caps and termination plugs are installed on unused ports.

  • X_S1_Air3

  • DC Power Connector is terminated correctly.
    Photos as required
    Grey connected to 0V and Black connected to -48V.
    Bootlace crimps used and connector correctly assemled to weather seal connector.

  • X_S1_Air4

  • DC Power Cable labled with external label as per the DRAN Installation MOP
    1 -2 Photos

  • X_S1_Air5

  • CPRI Fibre cables labeled as per the DRAN Installation MOP
    Photo

  • X_S1_Air6

  • Air Radios have correct Sector Label and Hazard Sticker
    Photos as required

  • X_S1_Air7

  • S1 RRH brackets
    1-2 Photos
    Installation of RRH brackets

  • X_S1_3

  • S1 RRH Earths
    2-3 Photos
    Photos of earth cables connected, and paste applied

  • X_S1_4

  • Photo of S1 LB radio 4499 BOA+B28
    1-2 Photos
    Photo of LB radio - labels readable

  • X_S1 LB

  • Photo of S1 HB radio 4499 Bl+B3
    2 Photos
    Photo of HB radio - labels readable

  • X_S1 HB

  • S1 NR Air 3278 or radio 8863
    1 Photos
    Photo of NR radio - labels readable

  • X_S1 NR

  • Is S2 Installed

  • S2 wide view
    1 Photos
    Wide view of sector showing radios and antennas

  • X_S2

  • S2 Bearing photo
    1-2 Photos
    Photo from top or side of antenna showing field of view (bearing)

  • X_S2 Azi

  • S2 Antenna brackets
    2 Photos
    Installation of antenna brackets

  • X_S2_2

  • Photo of S2 Antenna, Antenna label(s)
    2-4 Photos
    Photo of antenna and antenna label clearly showing antenna serial number

  • X_S2 Ant

  • Photo of S2 Antenna Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S2 Ant - M-Tilt

  • S2 NR Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S2 NR M-Roll

  • S2 - Sector information marked on antenna
    1 Photo
    Sector, Mechanical Tilt, Electrical Tilt, Azimuth and Height is marked

  • X_S2 Ant Info

  • S2 - ALD (RET) cable
    1-2 Photos
    Cable routed and connected correctly between the antenna and the High Band Radio 4499 B1+B3

  • X_S2 ALD

  • S2 - 3G/4G Antenna have correct Sector Label and Hazard Sticker
    1-2 Photos

  • X_S2 Ant Info 2

  • Has Air Equipment been installed on S2

  • Photo - AIR has been grounded with the double lug ground cable and lug screws have been tightened.

  • X_S2_Air1

  • Photo - AIR ground cable at grounding point has been terminated with the correct lug, correctly crimped and earth bonding paste used.

  • X_S2_Air2

  • Photo - Protective covers, dust caps and termination plugs are installed on unused ports.

  • X_S2_Air3

  • DC Power Connector is terminated correctly.
    Photos as required
    Grey connected to 0V and Black connected to -48V.
    Bootlace crimps used and connector correctly assemled to weather seal connector.

  • X_S2_Air4

  • DC Power Cable labled with external label as per the DRAN Installation MOP
    1 -2 Photos

  • X_S2_Air5

  • CPRI Fibre cables labeled as per the DRAN Installation MOP
    Photo

  • X_S2_Air6

  • Air Radios have correct Sector Label and Hazard Sticker
    Photos as required

  • X_S2_Air7

  • S2 RRH brackets
    1-2 Photos
    Installation of RRH brackets

  • X_S2_3

  • S2 RRH Earths
    2-3 Photos
    Photos of earth cables connected, and paste applied

  • X_S2_4

  • Photo of S2 LB radio 4499 BOA+B28
    1-2 Photos
    Photo of LB radio - labels readable

  • X_S2 LB

  • Photo of S2 HB radio 4499 Bl+B3
    2 Photos
    Photo of HB radio - labels readable

  • X_S2 HB

  • S2 NR Air 3278 or radio 8863
    1 Photos
    Photo of NR radio - labels readable

  • X_S2 NR

  • Is S3 Installed

  • S3 wide view
    1 Photos
    Wide view of sector showing radios and antennas

  • X_S3

  • S3 bearing photo
    1-2 Photos
    Photo from top or side of antenna showing field of view (bearing)

  • X_S3 Azi

  • S3 Antenna brackets
    2 Photos
    Installation of antenna brackets

  • X_S3_2

  • Photo of S3 Antenna, Antenna label(s)
    2-4 Photos
    Photo of antenna and antenna label clearly showing antenna serial number

  • X_S3 Ant

  • Photo of S3 Antenna Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S3 Ant - M-Tilt

  • S3 NR Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S3 NR M-Roll

  • S3 - Sector information marked on antenna
    1 Photo
    Sector, Mechanical Tilt, Electrical Tilt, Azimuth and Height is marked

  • X_S3 Ant Info

  • S3 - ALD (RET) cable
    1-2 Photos
    Cable routed and connected correctly between the antenna and the High Band Radio 4499 B1+B3

  • X_S3 ALD

  • S3 - 3G/4G Antenna have correct Sector Label and Hazard Sticker
    1-2 Photos

  • X_S3 Ant Info 2

  • Has Air Equipment been installed on S3

  • Photo - AIR has been grounded with the double lug ground cable and lug screws have been tightened.

  • X_S3_Air1

  • Photo - AIR ground cable at grounding point has been terminated with the correct lug, correctly crimped and earth bonding paste used.

  • X_S3_Air2

  • Photo - Protective covers, dust caps and termination plugs are installed on unused ports.

  • X_S3_Air3

  • DC Power Connector is terminated correctly.
    Photos as required
    Grey connected to 0V and Black connected to -48V.
    Bootlace crimps used and connector correctly assemled to weather seal connector.

  • X_S3_Air4

  • DC Power Cable labled with external label as per the DRAN Installation MOP
    1 -2 Photos

  • X_S3_Air5

  • CPRI Fibre cables labeled as per the DRAN Installation MOP
    Photo

  • X_S3_Air6

  • Air Radios have correct Sector Label and Hazard Sticker
    Photos as required

  • X_S3_Air7

  • S3 RRH brackets
    1-2 Photos
    Installation of RRH brackets

  • X_S3_3

  • S3 RRH Earths
    2-3 Photos
    Photos of earth cables connected, and paste applied

  • X_S3_4

  • Photo of S3 LB radio 4499 BOA+B28
    1-2 Photos
    Photo of LB radio - labels readable

  • X_S3 LB

  • Photo of S3 HB radio 4499 Bl+B3
    2 Photos
    Photo of HB radio - labels readable

  • X_S3 HB

  • S3 NR Air 3278 or radio 8863
    1 Photos
    Photo of NR radio - labels readable

  • X_S3 NR

  • Is S4 Installed

  • S4 wide view
    1 Photos
    Wide view of sector showing radios and antennas

  • X_S4

  • S4ing photo
    1-2 Photos
    Photo from top or side of antenna showing field of view (bearing)

  • X_S4_Azi

  • S4 Antenna brackets
    2 Photos
    Installation of antenna brackets

  • X_S4_2

  • Photo of S4 Antenna, Antenna label(s)
    2-4 Photos
    Photo of antenna and antenna label clearly showing antenna serial number

  • X_S4_Ant

  • Photo of S4 Antenna Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S4_Ant - M-Tilt

  • S4 NR Mechanical Tilt and Roll
    2 Photos
    Photo with Digital/inclinometer on front and top of antenna

  • X_S4_NR M-Roll

  • S4 - Sector information marked on antenna
    1 Photo
    Sector, Mechanical Tilt, Electrical Tilt, Azimuth and Height is marked

  • X_S4_Ant Info

  • S4 - ALD (RET) cable
    1-2 Photos
    Cable routed and connected correctly between the antenna and the High Band Radio 4499 B1+B3

  • X_S4_ALD

  • S4 - 3G/4G Antenna have correct Sector Label and Hazard Sticker
    1-2 Photos

  • X_S4_Ant Info 2

  • Has Air Equipment been installed on S4

  • Photo - AIR has been grounded with the double lug ground cable and lug screws have been tightened.

  • X_S4_Air1

  • Photo - AIR ground cable at grounding point has been terminated with the correct lug, correctly crimped and earth bonding paste used.

  • X_S4_Air2

  • Photo - Protective covers, dust caps and termination plugs are installed on unused ports.

  • X_S4_Air3

  • DC Power Connector is terminated correctly.
    Photos as required
    Grey connected to 0V and Black connected to -48V.
    Bootlace crimps used and connector correctly assemled to weather seal connector.

  • X_S4_Air4

  • DC Power Cable labled with external label as per the DRAN Installation MOP
    1 -2 Photos

  • X_S4_Air5

  • CPRI Fibre cables labeled as per the DRAN Installation MOP
    Photo

  • X_S4_Air6

  • Air Radios have correct Sector Label and Hazard Sticker
    Photos as required

  • X_S4_Air7

  • S4 RRH brackets
    1-2 Photos
    Installation of RRH brackets

  • X_S4_3

  • S4 RRH Earths
    2-3 Photos
    Photos of earth cables connected, and paste applied

  • X_S4_4

  • Photo of S4 LB radio 4499 BOA+B28
    1-2 Photos
    Photo of LB radio - labels readable

  • X_S4_LB

  • Photo of S4 HB radio 4499 Bl+B3
    2 Photos
    Photo of HB radio - labels readable

  • X_S4_HB

  • S4 NR Air 3278 or radio 8863
    1 Photos
    Photo of NR radio - labels readable

  • X_S4_NR

GPS Install

  • Photo of GPS Antenna
    1 -2 Photos
    Wide view of GPS antenna
    GPS receiver to be installed in a position with clear view of Northen sky.

  • X_GPS1

  • Photo of GPS Label
    1 Photo
    GPS Feeder labeled near GPS antenna as per DRAN Installation MOP

  • X_GPS2

  • View of GPS Antenna Bracket
    2-3 Photo

  • X_GPS3

  • N-Type Connections (f & m)
    2 Photos
    N-Type(f) connected to GPS feeder & N-Type(m) under Enclosure base frame and weatherproofed. Common practice is to put this in the enclosure - so no weather proofing required

  • X_GPS4

Technical Assurance

Pre Start Photos

  • General Photos of the site pre-start - 4 to 6 Photos of the site / compound and signage

  • X_PreStart

  • Are Cable Trays / Cable ladders installed?

  • Photos of exisitng Cable Trays / Cable Ladders Installed

  • X_PreStart_CableTrays

Enclosure Installs

  • Wide view of site enclosures
    1-4 Photos
    View of enclosures on plinth to view mount and cover plates

  • X_Enc1

  • Photo of enclosure 6140 door closed
    1 Photos
    View of enclosure 6140

  • X_Enc2

  • Photo of facilities cabinet door closed
    1 Photos
    View of facilities cabinet

  • X_Enc3

  • Photo of enclosure 6140 door open
    1 Photos
    View of enclosure 6140 layout

  • X_Enc4

  • Photo of facilities cabinet door open
    1 Photos
    View of facilities cabinet internals and install

  • X_Enc5

  • Photo of enclosure door label
    1 Photos
    Enclosure 6140 door label

  • X_Enc6

  • Photo of rectifier shelf, CB panel closed
    1 Photos
    View of rectifier shelf

  • X_Enc7

  • Photo of rectifier shelf, CB panel open
    1 Photos
    View of circuit breaker layout and install

  • X_Enc8

  • Photo of basebands - close up
    1 Photos
    View of basebands and install

  • X_Enc9

  • Photo of L-support bracket
    1-2 Photos
    View of L-support bracket - left and right

  • X_Enc10

  • Photos of batteries close up
    1 Photos
    View of batteries and INSTALL DATE

  • X_Enc11

  • Photos of battery L-support shelf / Rack
    1-2 Photos
    General photos to show batteries properly / securely installed

  • X_Enc12

  • Photo of SCU, SAU, CPS Rx and OVP-ALMB
    1 Photos
    View of SCU, SAU, CPS RX and OVP-ALMB

  • X_Enc13

  • Photo of incoming transmissions link
    1 Photos
    May require additional photos

  • X_Enc14

  • Photo of right inside of enclosure
    1 Photos
    View of AC cover panel in place and earth bar

  • X_Enc15

  • Photo of left inside of enclosure
    1 Photos
    View of battery cover panel in place

  • X_Enc16

  • Photo of ATS cable connected in RAN cabinet
    1 Photos
    View of ATS in RAN cabinet with label

  • X_Enc17

  • Photo of ATS cable connected in Utility cabinet
    1 Photos
    View of ATS in Utility cabinet with labels

  • X_Enc18

  • Rat / Ant bait
    3-4 Photos
    Photos of Bait and signs

  • X_Enc19

  • Photo of Earth Resistivity Table

  • X_Enc20

  • Photos of Ericsson cabinet hold down bolts

  • X_Enc21

  • Photos of Facility Cabinet hold down bolts

  • X_Enc22

  • Damp course or Plastic Shims - Erricsson Cabinet
    4-6 Photos
    Photo of DPC between Cabinet and plinth/ pad foundation

  • X_DPC

  • CoC, ROI, and Electrical Schematic
    2 Photos
    CoC, CDC in cabinet - for existing cabinets that do not have this info in the cabinet, please add a comment

  • X_CoC

  • Ducts / Conduits Sealed
    Photos as required to show sealing

  • X_Seal

Power Install

  • Photo of incoming power to enclosure
    1 Photos
    Enclosure AC power, cover removed to see incoming power connection - SHOULD BE TAKEN WHILE ELECTRICIAN IS ON SITE

  • X_Pow1

  • Photo of battery termination
    1 Photos
    Enclosure battery termination, cover removed to see termination

  • X_Pow2

  • Photo of AC Mains CB at MCB or facilities cable
    1 -3 Photos
    Overview of AC upgrade work

  • X_Pow3

  • DND tags on the power cable
    2-3 Photos
    Check DND Tag and clear photos

  • X_DND

  • Contact Paste on Earth Cables
    2-3 Photos
    Check Contact paste on cables and photos

  • X_Paste

  • Photos of cabinet eartths to EP/E with DND Tag

  • X_EPE

  • 35mm2 Enclosure Main Earth cable labeled
    1 Photo

  • X_Pow4

  • AC power breaker Label
    1 Photo
    Photo in cab to show what size it is (63A) and where the supply comes from- E2E

  • X_Pow5

  • Common earth cable labeled and contact paste added to external earth bar or utility cabinet earth bar
    (Paste not required inside Ericsson cabinet).

  • X_Pow6

  • CB Label is printed, laminated and attached to Inside of Heat Exchanger Door (Velcro or in Plastic Sleeve).

  • X_Pow7

Internal Equipment Install_Checks

  • Baseband Power cables have been neatly routed, connected and terminated to the correct circuit breakers as per the DRAN Installation MOP

  • All screws tightened to the correct torque.

  • SFP's installed correctly and in the allocated Baseband ports as per the DRAN Installation MOP

  • 2Degrees backhaul fibre transmission cable and 2Degrees supplied BiDi SFP installed into BB-1 TN-B

Cable Trays / Cable Ladders

  • Have cable trays been worked on or installed?

  • If new cable trays installed - Photos of Damp Course / Malfoid installed

  • X_DPC 3

  • Photos to show equipotential earth bonds for cable tray at cabinets and pole. Include earth bonds for cable tray joins and changes in direction

  • X_Equi Pot Bonds

  • Photos to show cable management on cable tray

  • X_Cable Tray 1

  • Photos to show pole / Pole Hatch modifications for cable entry

  • X_Cable Tray 2

  • Photos to show cable entry to cabinets

  • X_Cable Tray 3

  • Photos to show cable tray covers installed and secured

  • X_Cable Tray 4

  • Photos of hazard tape / signage on cable trays

  • X_Cable Tray 5

Cabling - Checks

  • All cable ties are cut flush with no sharp edges.

  • No cables are damaged.

  • Used only velcro on fiber cables - NOT Cable ties.

  • All cables have been labeled as specified in the D-RAN Installation MOP.

  • All DC cabling via the correct cable glands and neatly routed up the left side of the Enclosure as per the DRAN MOP

  • Rubber cable glands have been correctly opened - as per the DRAN Installation MOP - Photo to show install

  • X_Cabling1

  • All fibres and signalling cables neatly routed up the right side of the Enclosure as per the DRAN Installation MOP

  • X_Cabling2

Maintenance & Legacy Issues

Legacy Issues

  • "Are there any Legacy Issues NOT fixed as part of this build?<br>i.e. non-compliant build items from previous projects"

  • Legacy Issue 1

  • Short description of the issue

  • Photos of the issue (If applicable)

  • Legacy Issue 2

  • Short description of the issue

  • Photos of the issue (If applicable)

  • Legacy Issue 3

  • Short description of the issue

  • Photos of the issue (If applicable)

Maintenance Issues Identified

  • Are there any maintenance issues to be reported?

  • Maintenance Required - 1

  • Short Description of the issue

  • Photos of the issue (If applicable)

  • Maintenance Required - 2

  • Short Description of the issue

  • Photos of the issue (If applicable)

  • Maintenance Required - 3

  • Short Description of the issue

  • Photos of the issue (If applicable)

Sign Off

  • QA Checklist Completed

  • Name of Person Confirming Checklist Complete

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.