Information
-
Site Address
-
Job No.
-
Conducted on
-
Prepared by
Carpenter Details
Carpenter Details
-
Select Carpenter used on this job
- SY-Tunks Construction
- SY-DJH Carpentry
- SY-Czar Construction
- SY-Clark Building
- SY-Westbourne Developments
- SC-Darren Hansen Carpentry
- SC-Tapped Out
- SC-Nail It Carpentry
- SC-D & A Cupitt Building Services
- SC-Jamie Shaw Carpentry
- Other
-
Insert Carpenter (not shown on list)
Safety/General
General/Safety
-
1.01 Are all access way clear debris and material?
-
1.02 Is site fencing intact? (No Damage)
-
1.03 Is Lock on Gate?
-
1.04 Has all rubbish been placed in designated area including food scraps?
-
1.05 Has Timber Clean been conducted?
-
Book Timber Clean
Ground Floor
Pre Brick/Frame Inspection
-
1.01 Have all steel beams been adequately propped by scaffold?(T-bars over 3.6m to be propped by scaffold)
-
1.02 Have all trusses been installed?
-
1.03 Have all remaining timbers been stacked neatly?
-
1.05 Has steel posts been braced within straps and blocked out with timber?
-
105.1 Have all bracing straps been tightened and secured to framework?
-
1.06 Are steel posts adequately bolted/welded?
-
1.06.1 Are all windows/sliding doors installed?
-
1.07 Will top plates to steel posts interfere with cornice/square set?(check type of cornice)
-
1.08 Are all dyna bolts adequately secured? (check for adequate washers)
-
1.09 Are all noggins in place?
-
1.11 Have all windows been installed with galvanized bullet head nails? (note: collated framing nails are not acceptable)
-
1.12 Are sliding door sashes stacked neatly and secured?
-
1.13 Are glass panels free from scratches?
-
Advise relevant contractor of backcharge
-
1.14 Are frames free from scratches/dents?
-
Advise relevant contractor of backcharge
-
1.15 Are sliding door tracks protected?
-
1.16 Has plumbing rough in been completed?
-
1.17 Has bracing and triple grips been installed correctly? (Single/lower roof)
-
1.18 If niches are external walls, have they been blocked prior to brickwork?
-
1.19 Have double triple grips been installed to girder trusses? (Single/lower roof)
-
1.20 Have you accounted for any light points to brick piers? (Check electrical layout)
-
1.22 Has ground floor been swept and left over material stacked neatly?
-
1.23 Are all walls plumb and straight?
-
Single Storey Dwelling?
-
1.24 Has manhole been installed and location identified?
-
1.25 Have all shear blocks been installed?
COMMENTS
-
Are there any outstanding carpentry items?
-
Can This Job be Paid?
-
Insert Any Comments
SIGN OFF
-
Construction Supervisor Name
-
Complete next section for two storey.
First Floor
-
First Floor (please tick)
Pre Brick/Frame Inspection (First Floor)
-
1.01 Has first floor been swept and left over material stacked neatly?
-
1.02 Is void protection in place and ladder secured? (note: Ladder must protrude 900mm above platform)
-
1.03 Have all trusses been installed?
-
1.03.1 Are all noggins in place?
-
1.04 Have bulkheads been installed correctly? (Note: Some Bulkheads to be supplied by frame manufacturer and installed by frame carpenter)
-
1.05 Has manhole been installed and location identified?
-
1.06 Are all windows/sliding doors installed?
-
1.07 Have all windows been installed with galvanized bullet head nails? (note: collated framing nails are not acceptable)
-
1.08 Are sliding door sashes stacked neatly and secured?
-
1.09 Are there any scratches to glass panels?
-
Advise relevant contractor of backcharge
-
1.10 Are there any scratches/dents to all frames?
-
Advise relevant contractor of backcharge
-
1.11 Are sliding door tracks protected?
-
1.12 Has rough in been completed?
-
1.13 Have change of direction blocks been installed?
-
1.14 Has bracing and triple grips been installed correctly?
-
1.15 Have double triple grips been installed to girder trusses?
-
1.16 Have all bracing straps been tightened and secured to framework?
-
1.17 Have all shear blocks been installed?
-
1.18 If niches are external walls, have they been blocked prior to brickwork?
-
1.19 Has high load brackets been adequately bolted?
-
1.20 Has Dwarf wall to void been adequately secured? (stand alone dwarf wall is to be secured beyond flooring to LVL below)
-
1.21 Has safety handrail been used on job?
-
1.22 Are there any carpentry items that have not been completed? (write list if applicable)
COMMENTS
-
Are there any outstanding carpentry items?
-
Can This Job be Paid?
-
Insert Any Comments
SIGN OFF
-
Construction Supervisor Name