Information

  • Site Address

  • Job No.

  • Conducted on

  • Prepared by

Carpenter Details

Carpenter Details

  • Select Carpenter used on this job

  • Insert Carpenter (not shown on list)

Safety/General

General/Safety

  • 1.01 Are all access way clear debris and material?

  • 1.02 Is site fencing intact? (No Damage)

  • 1.03 Is Lock on Gate?

  • 1.04 Has all rubbish been placed in designated area including food scraps?

  • 1.05 Has Timber Clean been conducted?

  • Book Timber Clean

Ground Floor

Pre Brick/Frame Inspection

  • 1.01 Have all steel beams been adequately propped by scaffold?(T-bars over 3.6m to be propped by scaffold)

  • 1.02 Have all trusses been installed?

  • 1.03 Have all remaining timbers been stacked neatly?

  • 1.05 Has steel posts been braced within straps and blocked out with timber?

  • 105.1 Have all bracing straps been tightened and secured to framework?

  • 1.06 Are steel posts adequately bolted/welded?

  • 1.06.1 Are all windows/sliding doors installed?

  • 1.07 Will top plates to steel posts interfere with cornice/square set?(check type of cornice)

  • 1.08 Are all dyna bolts adequately secured? (check for adequate washers)

  • 1.09 Are all noggins in place?

  • 1.11 Have all windows been installed with galvanized bullet head nails? (note: collated framing nails are not acceptable)

  • 1.12 Are sliding door sashes stacked neatly and secured?

  • 1.13 Are glass panels free from scratches?

  • Advise relevant contractor of backcharge

  • 1.14 Are frames free from scratches/dents?

  • Advise relevant contractor of backcharge

  • 1.15 Are sliding door tracks protected?

  • 1.16 Has plumbing rough in been completed?

  • 1.17 Has bracing and triple grips been installed correctly? (Single/lower roof)

  • 1.18 If niches are external walls, have they been blocked prior to brickwork?

  • 1.19 Have double triple grips been installed to girder trusses? (Single/lower roof)

  • 1.20 Have you accounted for any light points to brick piers? (Check electrical layout)

  • 1.22 Has ground floor been swept and left over material stacked neatly?

  • 1.23 Are all walls plumb and straight?

  • Single Storey Dwelling?

  • 1.24 Has manhole been installed and location identified?

  • 1.25 Have all shear blocks been installed?

COMMENTS

  • Are there any outstanding carpentry items?

  • Can This Job be Paid?

  • Insert Any Comments

SIGN OFF

  • Construction Supervisor Name

  • Complete next section for two storey.

First Floor

  • First Floor (please tick)

Pre Brick/Frame Inspection (First Floor)

  • 1.01 Has first floor been swept and left over material stacked neatly?

  • 1.02 Is void protection in place and ladder secured? (note: Ladder must protrude 900mm above platform)

  • 1.03 Have all trusses been installed?

  • 1.03.1 Are all noggins in place?

  • 1.04 Have bulkheads been installed correctly? (Note: Some Bulkheads to be supplied by frame manufacturer and installed by frame carpenter)

  • 1.05 Has manhole been installed and location identified?

  • 1.06 Are all windows/sliding doors installed?

  • 1.07 Have all windows been installed with galvanized bullet head nails? (note: collated framing nails are not acceptable)

  • 1.08 Are sliding door sashes stacked neatly and secured?

  • 1.09 Are there any scratches to glass panels?

  • Advise relevant contractor of backcharge

  • 1.10 Are there any scratches/dents to all frames?

  • Advise relevant contractor of backcharge

  • 1.11 Are sliding door tracks protected?

  • 1.12 Has rough in been completed?

  • 1.13 Have change of direction blocks been installed?

  • 1.14 Has bracing and triple grips been installed correctly?

  • 1.15 Have double triple grips been installed to girder trusses?

  • 1.16 Have all bracing straps been tightened and secured to framework?

  • 1.17 Have all shear blocks been installed?

  • 1.18 If niches are external walls, have they been blocked prior to brickwork?

  • 1.19 Has high load brackets been adequately bolted?

  • 1.20 Has Dwarf wall to void been adequately secured? (stand alone dwarf wall is to be secured beyond flooring to LVL below)

  • 1.21 Has safety handrail been used on job?

  • 1.22 Are there any carpentry items that have not been completed? (write list if applicable)

COMMENTS

  • Are there any outstanding carpentry items?

  • Can This Job be Paid?

  • Insert Any Comments

SIGN OFF

  • Construction Supervisor Name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.