External Signs
-
Is all external signage including amenity boards and menu cabinets installed as DAG / LA approved drawings?
-
Are correct opening times up over main entrance?
-
Is the shop front fully opening and operating properly?
-
Has the statutory non smoking sign been installed to all entrances?
-
Is there enough luminance to the building and signage?
-
Is "History" plaque positioned externally adjacent front door?
-
Can all external front doors be secured in an open position?
-
Is smoking area completed with lighting / signage and bins?
-
Is bin / cage storage areas complete and enclosed from public view?
-
Has the opening date banner been installed?
-
Has external planting and irrigation system been installed and PPM information been noted for setting up?
Front of House
-
Has artificial internal planting been installed?
-
Is there enough local history?
-
Is every piece of artwork labelled with the artists name?
-
Has the Lloyds trading plaque been installed if applicable?
-
Is the Pub name explanation clearly detailed adjacent to main entrance?
-
Has the sculpture / WOW feature been installed?
-
Have extra stools been provided for the ends of booths etc?
-
Is there a defined bar walk?
-
Are all fire doors glazed and any other source of natural daylight maximised?
-
Have all thresholds been checked for tripping hazards?
-
Have door stops been installed to all Customer Area doors?
-
Is there adequate signage to WC's in place showing a clear route?
-
Is all fire fighting equipment in place?
-
Are vulnerable and / or low level walls protected?
-
Are child finger guards fitted to doors from customer area to the WC's?
-
(Hotel Only) Are finger guards installed on all corridor doors to rooms?
-
Do all banisters have studs / rope etc. to impede sliding?
-
Do all balustrades have gaps less than 100mm and no ladder effects are present?
-
Is Managers final exit alarm panel protected if positioned in the Customer area?
-
Has the dimming system been set up by the Electrician and Architect?
-
Please show pictures of lighting levels in pub and garden and send to Head of Development.
Bar Servery Areas
-
Are note detectors installed?
-
Are chip and pin terminals installed to bar top?
-
Are tills secured with brackets and to the correct detail?
-
Is the ice machine commissioned?
-
Is the glass wash area to the correct detail with skip and chute for bottles?
-
Has the coffee cup washer been set up to correct temperature?
-
Are all glass washers commissioning certificates with Site Agent?
-
Are all bar sundry items installed ? ( Bottle openers, post mix, illuminated badges etc )
-
Is bar signage package correct. Max 2x A4 frames and 1x A3 adjacent to bar?
-
Are the wine display boxes adequately illuminated?
-
Is the free pour section well illuminated?
-
Are the speed rails attached to each ice dump station?
-
Is there a fixed shot shelf below the free pour area 105mm high?
-
Are all other shelves adjustable?
-
Is there a kitchen screen visible from the bar servery?
-
Is the bar safe (if required) positioned within a lockable cupboard below a till station?
-
Is there at least one lockable cupboard to the front bar till pedestal ? (additional to bar safe )
-
Is there enough luminance to all display and bar areas?<br>
-
Is there a clock installed that is visible from the bar servery?
-
Does the coffee station include Water Boiler, Cold water tap, Milk Fridge, adequate storage and signage?
-
Have cellar services completed their install, and agreed a commissioning date?
-
Is the internal phone operational?
Toilet Area
-
Are sanitary bins installed?
-
Is full length mirror installed ?
-
Are walls tiled to a minimum of 2.1m high?
-
Is the A4 toilet check frame installed at far end of toilet?
-
Are soap dispensers installed?
-
Does ambulant cubicle have a pull handle?
-
Is vanity plumbing easily accessible for maintenance purposes?
-
To all cubicles have door stops and coat hooks?
-
Are there a minimum of 2 chrome handriers?
-
Is 1x urinal at lower level?
Disabled WC
-
Is sanitary bin installed?
-
Is full length mirror installed?
-
Are walls tiled to a minimum of 2.1m high?
-
Is A4 toilet check frame installed?
-
Is soap dispenser installed?
-
Does door have door stop and coat hook at appreciate height?
-
Is chrome handrier installed?
-
Is there a Doc M pack with contrasting handrails installed?
-
Is there a Doc M pull handle fixed to the door?
-
If baby change unit installed in Disabled WC is this an approved building control layout?
-
Has heating been installed?
-
Has a suitable shelf been installed?
Kitchen
-
Have all appliances been installed and commissioned?
-
Have gas appliances got a safety chain with star screw / fixing?
-
Has all equipment been installed as DAG approved kitchen plan and quotations?
-
Is pager system installed and working correctly?
-
Are food hoists installed and working correctly?
-
Are there sufficient screens installed in the kitchen and in the hoist area as DAG plan ? ( 2x if two floor trading )
-
Is the dry wipe board installed and visible from the cook line?
-
Is the clock installed and visible from the cook line?
-
Is the kitchen in / out door a minimum of 838mm?
-
Is the phone installed and working correctly?
-
Is the canopy fire suppression Ansul system installed and connected to the fire alarm?
-
Is Cheetah system installed to canopy and commissioned and functioning correctly?
-
Is grease pack installed and commissioned?
-
Please enter grease pack setting for record.
-
Is kitchen extract fully accessible for cleaning with doors at max 1.2m ?
-
Has the main gas pipe been painted inline with regulations?
Hoist Area
-
Is the screen and bump bar fitted?
-
Is heated gantry installed and working correctly?
-
Is dump station and bin installed?
-
Is plate rack storage fitted?
Office
-
Is shelving installed?
-
Is key cabinet installed?
-
Is safe installed?
-
Is spy hole installed to door?
-
Does door open out wards as preferred?
-
Has the lockable till draw cupboard been installed?
-
Is security equipment installed and working correctly?
-
Is ADSL Line / Box installed and working for Zonal?
-
Is ISDN Line / Box installed and working for Zonal?
Staff Room
-
Has pin board been installed?
-
Has clock been installed?
-
Has TV and did been installed?
-
Has furniture been installed?
-
Have lockers been installed?
-
Are there 18x coat hooks installed for staff use?
-
Is full length mirror installed?
Staff WC
-
Is handrier installed?
-
Is over basin mirror installed?
-
Has a knee operated sink been installed?
Staff changing rooms
-
Has timber bench been installed?
-
Has mirror been installed?
-
Has coat hook been installed to door?
General Store
-
Is shelving installed to all walls in store area?
Intruder Alarm
-
Is intruder alarm system completed?
-
Has intruder alarm remote signalling been tested?
-
Has intruder alarm full lock down been carried out and tested?
-
Has the fire alarm relay been wired and connected to the dualcom signalling system?
-
Is the intruder alarm connected to the internal lighting relay?
CCTV System
-
Is CCTV system complete?
-
Are any cameras blocked by either lighting or ornate features?
-
Has CCTV remote been tested?
Smokescreen
-
Is smokescreen installation complete?
-
Has smokescreen test been carried out?
-
Are smokescreen vinyls applied?
Plasma / Drop Down Screen
-
Is plasma / screen in correct position?
-
Has satellite dish / aerial installation been completed and agreed with Landlord / Agent on leasehold sites?
Audio Visual Specific
-
Is dance floor free of fixed seating and stackable furniture in place?
-
Is dance floor acceptable and without trips?
-
Is DJ unit fully installed ( if required )
-
Is sound web and jelly fish system installed?
-
Is lighting rig complete and structural loads from it approved by structural engineer?
-
Do speakers clash with light fittings?
-
Is the music rack in a naturally ventilated cupboard ( or cage within another room) ?
-
Is the light switch in DJ booth to switch off customer area lights adjacent to dance floor?
Cellar and Bottle store
-
Is soap / towel sundry items installed?
-
Is plain blackboard and cellar board installed?
-
Are CO2 / Nitrogen cylinders secured with a chain?
-
Is delivery route protected by aluminium chequer plate and angles to vulnerable corners?
-
Has cellar floor been checked for ponding?
-
Are all pipes protected?
-
Has the line cleaning unit been installed?
-
Are glycol coolers commissioned and A4 notices on wall for cleaning?
-
Is phone installed and working?
-
Has cold store temperature been achieved?
-
Has bottle store temperature been achieved?
External Area
-
Is delivery route clear of hazards and has level access?
General items
-
ALL FINAL ACCOUNTS TO BE RECEIVED BEFORE HANDOVER
-
Is building control application approved?
-
Has building inspector visited site and verbally approved works?
-
Are planning conditions approved in writing?
-
Has planning been received for the signage installation?
-
Has mechanical maintenance schedule been recieved?
-
Are noise conditions on planning approval discharged?
-
Has asset register been received for mechanical plant?
-
Has the Development Information Form for maintenance been completed?
-
Has asbestos survey and all clean air certificates been sent to ppmcertificates@jdwetherspoon.co.uk?
-
Has 2 copies of legal pack been prepared for issue? ( to be issued to JDW Estates on Monday following handover )
-
Have rear doors been fitted with hinge bolts and plated with steel sheet ? ( if required )
-
Are vulnerable external doors / windows protected with shutters ? ( if required )
-
Has snagging list been compiled along with any JDW additional items?
-
Have all contractors guarantees been provided ? ( roofs, cellar floors, windows etc )
-
Are all fire exit signs in place to all fire escape / doors?
-
Are action notices applied to all break glass points?
-
Have Mains Gas Services been checked and commissioned?
-
Have Mains Electric services been checked and commissioned ?
-
Have Mains Water services been checked and commissioned?
-
Have Mains Drainage Services been checked and commissioned?
-
Has drainage report from main contractor been received and confirmed that all works completed?
-
Have Extract Awairs comments been actioned?
-
Please add photos to confirm full access to fan and ductwork for cleaning
-
Have PIRs been fitted to all back of house and duct lighting ? ( timed switches to plant areas and ducts if required )
-
Has fire detection been installed to all voids?
-
Has a low pressure switch installed to the central heating system?
-
Have mechanical and electrical maintenance contractors been invited to handover to give recommendations?
-
Have AM / GM and Pub Team been invited to handover?
-
Does plant conform to Acoustic / EHO / Planning requirements and been tested?