Information

  • Document No.

  • Inspection type

  • Client/Site

  • Conducted on

  • Onsite
  • Prepared by

1 - Building Management System

  • BMS has no major alarms or faults?

  • Photo of BMS alarm screen

  • Check AHU screen for any faults, all ok?

  • Photo of AHU screen

  • Check all VAV's are running and have no faults (??), all ok?

  • Are the major plant running?

  • Photo of chilled or heating plant

  • Note defects.

2 - Pulse Tech

  • Under the "OH&S Risk Management" tab all overdue risk items have or will be completed?

  • Under "Building Summary" tab have all overdue work requests been extended or closed off completed?

  • Have all tenant requests been acknowledged in the tenant portal section?

  • Have all completed work requests been closed off?

  • Have all scheduled planned jobs been released to work in progress and PO's send to contractors?

  • Have all work requests been completed by contractors in an acceptable time frame?

  • Note defects.

3 - Level 12 - Plant rooms

3.1 - Domestic hot water system

  • Is the plant room leak free?

  • Is the plant room safe and free of any risk hazards?

  • Secondary hot water loop pump is operational?

  • Temps are above 65 Celsius?

  • Note defects.

3.2 - Air handling units

  • Is the plant room leak free?

  • There are no loose V belts, pulleys are abnormal noises?

  • Is the plant room safe and free of any risk hazards?

  • Are the VSD's fault free?

  • Note defects.

3.3 - Boiler plant

  • Photo of boiler plant

  • Is the plant room leak free?

  • Are the VSD's fault free?

  • Is the plant room safe and free of any risk hazards?

  • Are the boilers operational?

  • Note defects.

3.4 - Chiller plant

  • Photo of chiller plant

  • Is the plant room leak free?

  • Are the VSD's fault free?

  • Is the plant room safe and free from any risk hazards?

  • Are the chillers in operation?

  • Note defects.

3.5 - Trigen plant

  • Photo of trigen plant

  • Is the plant room leak free?

  • Are the VSD's fault free?

  • Is the plant room safe and free of any risk hazards?

  • Is the generator preheating working?

  • Note defects.

3.6 - Cooling towers

  • Photo of cooling towers

  • Is the plant room leak free?

  • All chemicals have acceptable levels?

  • No signs of chemical leak?

  • There are no faults on the Dosing unit?

  • Are the VSD's fault free?

  • Are the plant rooms safe and free of any risk hazards?

  • Note defects.

4 - Ground floor and basement - Plant

4.1 - Gas meter room

  • There is no signs of a gas leak?

  • Gas mains is running?

  • Note defects.

4.2 - Fire plant rooms

  • No sign of any diesel leaks?

  • Diesel and electric booster pumps are ready and fault free?

  • Pump/valve sets are maintaining pressure above 1200 kPa

  • Photo of pressure

  • There are no unauthorised isolations?

  • Fire indication panel is free from faults?

  • Photo of FIP

  • Note defects.

4.3 - Grey water plant room

  • Photo of grey-water plant

  • Is the plant room leak free?

  • Is the plant room safe and free of any risk hazards?

  • Any signs of bad smells?

  • Is the plant room safe and free of any risk hazards?

  • Note defects.

4.4 - Rainwater pump room

  • Photo of rainwater plant

  • Is the plant room leak free?

  • Is the plant room odour free?

  • Pumps are operational or not in fault?

  • Is the plant room safe and free of any risk hazards?

  • Note defects.

4.5 - Main switch room

  • Photo of switch room

  • Is the plant room leak free?

  • Is the plant room safe and free of any risk hazards?

  • Note defects.

4.6 - Mezzanine plant rooms

  • South plant room

  • Centre plant room

  • North plant room

  • Is the plant room leak free?

  • Are the VSD's fault free?

  • Fan coil units are operational?

  • Is the plant room safe and free of any risk hazards?

  • Note defects.

4.7 - Diesel generator

  • No faults on the high level interface?

  • Photo of high level interface

  • Is the plant room leak free?

  • Is the generator preheating working?

  • Is the plant room safe and free of any risk hazards?

  • Note defects.

5 - Vertical Transport

  • Test lift emergency alarm, does it dial out to the 24 hour call centre?<br>

  • Is the BMS fault free?

  • Photo of BMS screen

  • Note defects.

6 - DEEWR property operations team

  • Are there any outstanding work requests or issues?

  • Touch base and make sure they are happy?

7. Diesel pump room

  • Photo of pumps

  • Is there any sign of leaks?

  • Note defects.

8 - Sign off

  • Add signature

  • Select date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.