1.00 PRE-COMMENCEMENT REPORT
1.01 Demolition
-
Demolition completed?
-
If No, Client to advise of Demolition date
1.02 Rubbish/Debris
-
Rubbish/debris to be removed?
-
If Yes, Client to advise of removal date.
1.03 Grass/vegetation
-
Grass/vegetation to be cut prior to starting work?
-
If Yes, Client to advise of removal date.
1.04 Trees
-
Trees on site to be removed prior to starting work?
-
If Yes, Client to advise of removal date.
1.05 Footpath
-
Damage to footpath? (take pic either way)
-
If Yes, Client to note.
1.06 Kerb & Gutter
-
Damage to kerb & gutter? (take pic either way)
-
If Yes, Client to note.
1.07 Boundary Fence
-
Is there damage to boundary fence? (take pic either way)
-
If Yes, Client to note.
1.08 Fill
-
Excess fill to be removed following excavation? (please note approx loads)
-
Fill required? (please note approx loads & check contract for PA)
-
If Yes, Extra costs may be incurred. Client to be present on date of removal/importation to monitor.
1.09 Rock Shelf
-
Can rock shelf be seen?(if Yes, take photograph)
-
If Yes, excess costs may be incurred for rock breaking and removal
1.10 Power lines
-
Power lines-tiger tail insulation required?(if Yes to service main or service to house? If unsure notify WHS Manager for safety assessment)
-
If Yes, excess costs may be incurred.
1.11 Cranes
-
Extra cranes required?
-
Would normal deliveries be affected due to site conditions?
-
If Yes, excess costs may be incurred for double handling and crane hire.
1.12 Traffic Control
-
Is traffic control required(if Yes check contract for PA)
-
If Yes, excess costs may be incurred.
1.13 Retaining Walls
-
Is a retaining wall required after site is excavated? (if Yes Fowler to assess and immediately advise client)
-
Note: Excavations over 1m in depth will not start unless there is prior consultation with Fowler Homes Pty Ltd
Supervisor Sign off
-
I supervisor of above mentioned site certify items raised in this report are true and correct as of date below
-
Signature
2.00 Internal Use Only
-
Is site within 1km of the ocean or non surf coast?(if yes check contract and selections)
-
Is site classified as tight site?(if Yes what trades will be affected?)
-
Sewer affected? (supervisor to check plans, if Yes ensure all plans are correct)
-
Are all pegs in place?
-
Is Tree protection zone Required?
-
All weather access on site ordered?
-
Is existing boundary fencing 1.8m high?
-
Fencing ordered?
-
Sketch boundary where temporary fence is required
-
Water on site?
-
Have you organized Safety Signage, Padlock and WHS Management Plan for site? (advise WHS Manager)
-
Is site in close proximity to school or park?(if Yes notify WHS Manager)
-
Is traffic management plan required?
-
Will scaffold require shade cloth?(if Yes notify scaffolder)
-
Would normal deliveries be affected due to site conditions? (internal note: if Yes, supervisor to contact transport company prior to frame delivery)
-
Does site have existing pool?
-
I have read and understood all items on DA.
-
CSO to sign once read and actioned
COMMENTS
-
Comments/recommendations
-
Signature