Information

  • Document No.

  • PROJECT NAME

  • AHB PROJECT NUMBER

  • Conducted on

  • Prepared by

  • Location
  • Personnel on worksite

AHB SUPERINTENDENT

PERSONAL PROTECTIVE EQUIPMENT

  • Hard hats (with bills forward)

  • Safety glasses appropriate for conditions (tinted or clear)

  • Hard toe work boots

  • Reflective vests

  • Gloves

  • Hearing protection if required

  • Face shields for cutting or grinding

HOUSEKEEPING

  • General site storage and housekeeping

  • Trash cans in work area

  • Spoil piles maintained

  • Storage / Dog House orderly

  • Safe walkways or passages

TEMPORARY BARRICADES

  • Proper tape used (red for danger, yellow for caution)

  • All sides of work area barricaded and labeled

LADDERS AND ELEVATED WORK

  • Ladders tied off

  • Ladder extended 3'

  • Inspected and tagged

  • Components undamaged

  • Handrail in place

FALL PROTECTION

  • Harness and lanyards used

  • Harness and lanyards inspected and within useable life

  • Hole protection used during work hours

  • Proper hole protection used after hours

MOBILE EQUIPMENT

  • Equipment inspected prior to initial use each shift

  • Seatbelts used

  • Workers trained

  • Annual inspections as required

  • Backup alarms working

  • Spotters used when needed

  • Equipment maintained without leaks

  • Safety guards and covers in place

  • Whip-checks used on pressurized lines

  • Spill kits available

HOISTING AND RIGGING EQUIPMENT

  • Daily crane inspection performed

  • Annual inspection placard and operators manuals available

  • Proper rigging and techniques used

  • Sling/chokers properly stored

  • Slings/chokers inspected

  • Qualified rigger named

  • Safety latch on hook checked

  • Workers staying clear of suspended loads

  • Knowledge of crane signals

  • Proper use of tag lines on suspended loads

  • Swing protection in place

EXCAVATION

  • Shaft stability measures properly used (casing, fluid level maintained, drill mud within specs, etc)

  • Spin off area maintained

  • Equipment staged a safe distance away overnight

  • Workers trained

REBAR PLACEMENT

  • Lifting plan properly planned, communicated and managed by a designated lift supervisor

  • Cage properly prepared with #9 wire and clamps

  • Cage properly rigged for lifting

  • Cage lifted and secured in shaft safely

CONCRETE OPERATIONS

  • Concrete pump and hoses used properly

  • Slick lines and hoses properly clamped with safety wire

  • Concrete washed from skin contact

PREWORK

  • Weekly Toolbox Talks are relevant to the Project, and sign-in sheets are submitted

  • Safe Work Plan was communicated to all workers on the project for tasks performed

  • MSDS for all chemicals on the project are available upon request

  • Supervisors are aware of local first-aid and hospital facilities

  • All required jobsite work permits, hot work permits, excavation permits, etc are obtained and dated properly.

  • Underground locates are in place and current

  • First Aid Kit is on site, in a sanitary condition and available for all workers on the Project

  • Employee training records are available for work being performed

REPRIMANDS OR WARNINGS

  • We're any reprimands issued?

  • We're any verbals warnings or directives given?

  • Was any Stop Work order issued?

COMMENTS

  • Add media

INSPECTION PERFORMED BY:

  • Add signature

INSPECTORS TITLE

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.