Has the non return valve been installed on the new internal mains cold water supply to the pump panel?
-
Non Return Valve picture
-
Has the isolation valve been installed on the new internal mains cold water supply to the pump panel?
-
Isolation valve picture
-
Is the new internal/external mains cold water pipework to the pump panel adequately supported along its length?
-
Internal pipework support picture
-
Is the new external water pipework from the pump panel to the chiller(s) adequately supported along its length
-
External pipework support picutre
-
Has the external mains cold water pipework been insulated?
-
Pipework insulation picture
-
Has the new MCB in the distribution board been labelled (not hand written)?
-
MCB label picture
-
Have the UV Bulb details been recorded on the bulb matrix
-
UV Bulb details/Matrix - Picture
-
Is the bulb matrix affixed inside of panel?
-
Bulb matrix picture
-
Is the pump panel fitted correctly and adequately supported?
-
Panel picture
-
Is the cable to the pump panel adequately supported?
-
Cable support picture
-
Has the pump panel electrical isolator been installed?
-
Panel electrical isolator picture
-
Has fire sealant been used where pipework/cable penetrates a fire compartment?
-
Fire sealant picture