Title Page
-
Site
-
Started on
-
Inspected by
-
Subcontractor
-
Foreman
-
Works Certified
-
Completed on
PRE WORK CHECKS A
-
CORRECT LIGHT SCHEDULE ON SITE
-
SET OUT AND MARK LIGHT POSITIONS IF NECESSARY
-
SITE CLEAN
FINAL FIX INSTALATION A
-
ALL PLUGS AND SWITCHES LEVEL AND PLUMB
-
DB NEAT AND LABLED
-
ADEQUATE FIXINGS FOR STOVE, HOB AND EXTRACTOR
-
STOVE, HOB AND EXTRACTOR PLUMB AND LEVEL
-
ADEQUATE FIXINGS FOR LIGHT FITTINGS
-
LIGHT FITTINGS LEVEL AND STRAIGHT
-
COC TEST DONE AND CERTIFICATE SIGNED
PRE WORK CHECKS B
-
PAINTWORK INTERNAL FINAL PHASE CERTIFICATE COMPLETE
-
SITE CLEAN
FINAL FIX INSTALATION B
-
RE TEST ALL PLUGS, LIGHTS, STOVE, HOB AND EXTRACTOR
-
ALL GLOBES INSTALLED
-
FIT PLUG AND SWITCH COVERS
GENERAL
-
HOUSEKEEPING – ONGOING, ALWAYS DO PRE WORK CHECK AND REPORT IF WORK AREA IS NOT CLEAN. AFTER WORK HAVE STARTED HOUSEKEEPING FOR WORK AREA IS YOUR RESPONSIBILETY!!!!!
-
REQUIRED PPE
-
SAFETY FILE UP TO DATE
APPROVALS
-
SUBCONTRACTOR SIGNATURE
-
FOREMAN SIGNATURE