Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
-
Instructions
-------------------
1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
Rockwool fire barriers
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
Rockwool fire barrier materials
-
Fire barrier schedule is available<br>within the site documentation
-
Personnel
- Installer
- A2O
-
Fire barrier materials have been<br>checked on delivery to site to be<br>correct type and specification in<br>accordance with the A2O fire barrier<br>schedule
-
Personnel
-
Fire barrier materials have been<br>stored on site in an appropriate<br>manned in accordance with<br>manufacturers recommendation.<br>"Keep material in original packaging<br>until it is to be used. Store material<br>to protect against<br>damage including the weather"
-
Personnel
-
All fire barrier brackets, fixings and<br>tape has been delivered to site and<br>checked that they are in accordance<br>with the A2O fire barrier schedule<br>and manufacturers specification.
-
Personnel
Pre-installation
-
A site meeting with fire barrier<br>supplier [Rockwool] arranged and<br>carried out in advance of installation<br>works commencing. To include any<br>training that may be required.
-
Personnel
- Installer
- A2O
-
A2O Fire barrier construction<br>drawing are on site within the A2O<br>drawing file.
-
Personnel
- Installer
- A2O
-
All installation operatives have been<br>briefed (toolbox talk)on the specific installation of<br>the fire barriers to be installed, in<br>accordance with manufacturers<br>recommendation
-
Personnel
Vertical Fire barrier installation
-
Check fire barrier locations are in<br>accordance with A2O fire barrier<br>setting out construction drawings.
-
Personnel
- Installer
- A2O
-
Check that brackets 75% penetrating through the barrier and installed at max 500mm centers and max 250mm from the end of the barrier and fixed with noncombustible fixing as per A2O fixing schedule.
-
Personnel
- Installer
- A2O
-
check that thickness of fire barrier is in<br>accordance with cavity void and<br>extra 10 mm for the compression is been aloud , in<br>accordance with the manufacturers<br>specification.
-
Personnel
- Installer
- A2O
-
Ensure that the fire barrier is tightly<br>abutted to the barriers to each side<br>and seal the joints with foil tape.
-
Personnel
- Installer
- A2O
-
Installation of horizontal fire barrrier
-
Make sure than horizontal fire barrier get installed after the vetical
-
Personal
-
Manually fold brackets 90 degrees at a point to<br>allow the correct embedment into<br>the fire barrier. This needs to be<br>75% penetrating through the barrier .
-
Personnel
- Installer
- A2O
-
Check min 2 brackets per one fire barier length and bracket are fixed at max 500mm centers with noncombustible fixing as per A2O fixing scheduled.
-
Personnel
- Installer
- A2O
-
Check min 3 pigtail screws been installed at max 333 centers. These screws should protrude from the front face of the barrier by a maximum of 25mm.<br>
-
Personal
-
Ensure that the fire barrier is tightly<br>abutted to the barriers to each side<br>and seal the joints with foil tape.
-
Personnel
- Installer
- A2O
Completion
-
Installer Signature:
-
A2O Signature:
-
Client Signature: