Title Page

  • Site conducted

  • Audit Title

  • Project Name

  • Conducted on

  • Prepared by

  • Location
  • Instructions
    -------------------
    1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
    2. Add photos and notes by clicking on the paperclip icon.
    3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
    4. Complete audit by providing digital signature.
    5. Share your report by exporting as PDF, Word, Excel or Web Link

Tenmat Firebarrier

  • Project Number:

  • Issued to:

  • QA Sheet No:

  • Elevation:

  • Level:

  • Comments:

Tenmat fire barrier materials

  • Fire barrier schedule is available<br>within the site documentation

  • Personnel

  • Fire barrier materials have been<br>checked on delivery to site to be<br>correct type and specification in<br>accordance with the A2O fire barrier<br>schedule

  • Personnel

  • Fire barrier materials have been<br>stored on site in an appropriate<br>manned in accordance with<br>manufacturers recommendation.

  • Personnel

  • All fire barrier brackets, fixings and<br>tape has been delivered to site and<br>checked that they are in accordance<br>with the A2O fire barrier schedule<br>and manufacturers specification.

  • Personnel

Pre-installation

  • A site meeting with fire barrier<br>supplier (Tenmat / Galaxy insulation) arranged and carried out in advance of installation works commencing. To include any training that may be required.

  • Personnel

  • A2O Fire barrier construction<br>drawings are on site within the A2O<br>drawing file.

  • Personnel

  • All installation operatives have been<br>briefed on the specific installation of<br>the fire barriers to be installed, in<br>accordance with manufacturers<br>recommendation

  • Personnel

Fire barrier installation

  • Check fire barrier locations are in<br>accordance with A2O fire barrier<br>setting out construction drawings.

  • Personnel

  • At each fire barrier location, check<br>that thickness of fire barrier is in<br>accordance with cavity void plus<br>compression allowance in<br>accordance with the manufacturers<br>specification.

  • Personnel

  • Bracket fixings are fixed at 500mm<br>centres with non combustible fixings<br>[no plastic or rubber washers].<br>Ensure fixings are as per A2O or<br>manufacturers specification.

  • Personnel

  • Ensure that the fire barrier is tightly<br>abutted to the barriers to each side and brackets do not stop compression of barrier.

  • Personnel

  • Fire mastic to seal any voids behind studs. Fire mastic to be approved by tenmat (rockwool firepro acoustic intu sealant)

  • Personnel

  • Bespoke items

Completion

  • Installer Signature:

  • A2O Signature:

  • Client Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.