Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
-
Instructions
-------------------
1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
Structural Framing System
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
STRUCTURE
-
Primary Structure handover complete.
-
Personnel
- Installer
- A2O
BASE AND HEAD TRACK
-
Base & Head Track: Steel gauge in accordance with A2O working drawings
-
Personnel
- Installer
- A2O
-
Base & Head Track fixed to concrete/steel in accordance with A2O working drawings.
-
Personnel
- Installer
- A2O
GENERAL STUD
-
General Stud: Steel gauge in accordance with A2O Drawings
-
Personnel
- Installer
- A2O
-
Head Detail: Stud to be fixed to head track to facilitate structure deflection in accordance with A2O working drawings.
-
Personnel
- Installer
- A2O
-
Base Detail: Stud to be fixed to base track in accordance with A2O workding drawings.
-
Personnel
- Installer
- A2O
JAMBS/CILLS/LINTELS/NOGINS
-
Jamb/Cill/Lintel: Steel gauge/sizes in accordance with A2O working drawings.
-
Personnel
- Installer
- A2O
-
Single/Compound Jamb: Fixings at head and base in accordance with SFS Standard Details. Extra fixing may be required at jamb studs/track. Refer to project-specific A2O details.
-
Personnel
- Installer
- A2O
-
Single/Compound Cill/Lintel: Fixings at jamb in accordance with SFS Standard Details. Extra fixing/angle may be required at jamb studs. Refer to A2O working
-
Personnel
- Installer
- A2O
-
Compound Jamb/cill/Lintel: Boxed sections to be filled with Infill Insulation
-
Personnel
- Installer
- A2O
-
Nogins/Blocking installed in accordance with A2O drawings.
-
Personnel
- Installer
- A2O
Cement Particle Board
-
Confirm 12mm Versaliner SF board is being used as A2O drawings.
-
Personnel
- Installer
- A2O
-
Versaliner board fixings to SFS to be at maximum 600mm centres.
-
Personnel
- Installer
- A2O
-
Joints in boards sealed with versa sealer and foil tape.
-
Personnel
- Installer
- A2O
Completion
-
Installer Signature:
-
A2O Signature:
-
Client Signature: