Title Page

Client and System Infomation

  • Customer Name

  • Address
  • Contract Number

  • Date of Install

  • System Type (Make/Model)

Readings Sheet

Access Control Readings and Testing sheet

  • Instructions

    1. complete the sections Fully.
    2. Add Photos in ""Images"" and Comments in ""Notes"" on each question, AS REQUIRED
    3. Add a Corrective Measure in ""Action."" if there are any actions to be carried out by Customer
    4. Complete the by providing a digital signature by the installing engineer and the customer

Controlled door information

  • Add Door Information

  • Door

Door 1 Information

  • Access Point Classification (NCP109 Clause4.3)

  • Parent ACU UID/Serial number

  • Door Location

  • Read in type :

  • Reader IN Voltage

  • Door exit method ( RTE/Reader)

  • Reader OUT Voltage

  • Door Release time

  • Door Monitoring installed

  • Type ( select all that apply )

  • door held open delay

  • Door forced alarm duration

  • Door Lock Type

  • Provide details

  • Lock Voltage

  • Door Lock Override facility

ACU Main Control unit Equipment and Power supply tests

  • Add ACU Information

  • ACU

ACU 1

  • ACU TYPE

  • ACU Location

  • ACU Serial number/UID number

  • Number of doors the ACU can control

  • ACU IP Address ( If applicable )

  • PSU Charging Voltage .................. Vdc

  • PSU Battery/AUX Voltage Current .................mA

  • Battery Capacity fitted if applicable

Entry Phone System system

  • Entry phone system installed ?

Entryphone System installed

  • System Type

External Call stations

  • Add Call station :

  • Call Station

External Station 1

  • Location

  • Video or Audio only

  • ID number /IP address :

  • Linked to internal station

Internal Handsets

  • Add Internally fitted handset information

  • Answer station

Handset 1

  • Location

  • Video or Audio only

  • ID number /IP address :

PC's

  • Add PC'S controlling database

  • PC
  • PC Location

  • PC IP address :

  • Is PC Running Software as a Server or as Client

  • Firmware/Software version number

3rd Party Interface's

  • Fire Alarm Door override relays

  • Provide Details

  • CCTV control link

  • Provide Details and locations

  • Intruder Alarm link

  • Provide Details and locations

  • BMS System Interface

  • Provide Details and locations

Inspection checklist

  • Cabling has been carried out following wiring regulations (BS7671) on how cables are supported in the event of a fire I.E metal clips/ties used to support cable along the entire route to prevent premature collapse.

  • Give details as to why not applicable

  • Network cables have been tested for Wire mapping, Short/Open circuits and terminated as per T568B colour codes

  • If a complex structured network is Installed full certified test records are completed and supplied

  • Ensure the system is logging all Access/Egress and attempted access events in the event log.

  • Cables, connectors, patch panels, termination blocks and outlet sockets all compatible, i.e., Cat 5e and Cat 6 components and cables should not be mixed.

  • Checked and recorded the Normal and Door Unlocking DC/AC loading readings

  • Mains supply connected to an Unswitched Spur - If left on Plug awaiting spur to be fitted make a note and obtain customer signature

  • Check Supply fuses to the installtion have the correct rating

  • Check batteries are clearly marked with date of installation ( if fitted )

  • Remove mains supply and check the battery supply voltage of all equipment is within the specified limits of the manufacturers equipment and the system operates normally

  • Check the operation of Each access point device ( Reader/keypad/Biometrics)

  • Ensure Release time for each door is recorded and does not exceed 10s

  • confirm the correct alarm conditions are correctly indicated

  • check verification of access levels by input of appropriate data in database

  • Check all emergancy release function work correctly

  • Check all devices are fitted to meet DDA complient levels (1.3m +/- 300mm)

  • Check that all suplus material and equipment is cleared from site and that the customers premises have been left tidy

  • take pictures of work areas

  • Are door ACU's fitted within the secure area

  • Have you informed the customer that any documents left on site may contain personal information about there security and should be stores securely, as per ISO 27001 & GDPR Policy

Handover

Amendments to specification

  • confirm that the Requirements of NCP 104 and BS EN 50132-7:1996 and all other relevant requirements are met and any changes to the specification are agreed and documented

  • add detail for each alteration
  • Details of Changes to specification

Completion certificate

  • User's trained

  • User trained

  • User
  • Add signature

  • User guide supplied

  • Number of Fobs/Codes/Cards supplied

Final sign off

  • I Sign to confirm that :
    -->I am happy to accept the installed system and that I have been given a demonstration and am happy with how the system works and what to do in the event of malfunction
    -->I agree that the site has been left clean and tidy
    -->The system has been left fully operational.
    -->There is a need to take regular backups of the system (especially after changes to user access levels or adding/removing users)
    -->Periodic maintenance of door furniture and correct operation of door closers is our (the user's) responsibility
    -->Where Interfaced with the fire alarm system it is our (the user's) responsibility to ensure the doors are released during the weekly tests
    -->We (the users) will ensure that emergency release units are not misused and rest after false use.
    --> We are happy with the Installing company retaining any codes/Access information required for ongoing maintenance.
    --> We are aware of the DPA and UK GDPR legal requirements
    -->The system has been left fully operational.
    --> Payment in full will be made as per agreement.

  • Customer/Customer's representative's Name & Signature

  • Engineer Name & Signature

  • Date of Handover

  • following the completion of works the following will be issued within 30 days:
    --> NSI Certificate of Compliance - A trusted mark showing the system has been installed in line with the highest standards.
    --> Customer Satisfaction survey

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.