Framing
-
Is Framing Inspection Complete both by City Official and Structural Engineer?
-
Are all walls straight edged and planed?
Electrical
-
Electrical inspection has been performed and approved?
-
All Nail Plates are correctly installed?
-
Fire Protection has been installed around all conduit/MC cable above ceiling and walls?
-
All gypsum board in fire rated partitions due to due to electrical conduit/MC cable installation is free from damage?
-
Any and all blocking used by subcontractor is complete?
-
All boxes have the proper support ears for the partition type they are in, secure, and in the right location?
Plumbing
-
Plumbing inspection has been performed and approved?
-
All water lines have been tested?
-
Fire protection has been installed around all plumbing lines above ceilings in fire rated partitions?
-
All Plumbing lines are strapped correctly
-
All nail plates are correctly installed?
-
All gypsum board in fire rated partitions due to piping installation is free from damage?
-
Any and all blocking used by subcontractor is correctly installed?
Sprinkler
-
Sprinkler inspection has been performed?
-
All penetrations through fire rated partitions above ceiling level have had fire protection installed?
-
All sprinkler lines ave been tested?
-
All sprinkler heads have been capped off?
-
Water has been placed into the system, tested at 200 PSI for 2 hours and holding?
HVAC
-
HVAC inspection has been performed?
-
All penetrations through fire rated partitions above ceiling level have had fire protection installed?
-
All duct penetrating the exterior walls have been properly sealed?
-
All duct supply drops and returns are in the correct area?
-
All Flex Duct is properly secured?
-
Line Sets are Run and tested?
-
All condensate Drains are slopped and completed?
Low Voltage
-
Low voltage inspection has been performed?
-
SOHO Box is installed and in proper location
-
All penetrations are properly fire sealed?
-
All boxes are in the correct location and secure?
-
All gypsum board in fire rated partitions due to wiring installation is free from damage?
Insulation
-
All Rock Wool is in place for fire blocking on Party Walls?
-
All Rock Wool is in place on Plumbing Walls where needed?
-
Rock Wool is in place under Tub Drain?
-
All Insulation in Ceiling and Walls are installed with Proper R Value?
General
-
All trade inspections have been accounted for?
-
All blocking and/or strapping in fire rated partitions is fire rated wood?
-
All windows have been waterproofed?
-
Unit is Broom Clean and Ready for D/W
Review
-
Follow up Notes
-
Plumbing Contractor Signature
-
Select date
-
Electrical Contractor Signature
-
Select date
-
HVAC Contractor Signature
-
Select date
-
Low Voltage Contractor Signature
-