Information
-
Report Reference Number:
-
Site Name/ Location:
-
Client
-
Conducted on
-
Inspected by:
-
Accompanied by:
-
Scoring.
N/A = This item was not applicable at the time of the inspection, or it was not one of the items inspected.
S = Satisfactory. This category was being managed / controlled in accordance with minimum requirements or better.
A = Advisory. Recommended measures necessary to achieve industry best practice.
IAR = Immediate action required to reduce the risk of harm and/or enforcement action.
Accidents, Dangerous Occurrences or Near Misses since last visit.
-
Number recorded. :- Provide details.
0 Previous Inspections.
-
Has previous inspection been satisfactorily addressed/ Closed out.
-
Recommended Actions.
1 Scaffolds and Mobile Towers
-
Designed /TG20 compliance sheet- hand over certificates- erected in accordance with recognised standards SG4- statutory inspections carried out etc.
-
Recommended Action.
2 Ladders, Stepladders, Podiums etc.
-
Fit for purpose - in good order - secured - inspected etc.NMAE
-
Recommended Actions.
3 Demolition.
-
Demolition plan in place - work carried out in accordance with plan etc.
-
Recommended Action.
4 Excavations & Groundworks.
-
Safe digging practices- supported/battered - statutory inspections - access/egress etc. No dig technology
-
Recommended Action.
5 Lifting Operations.
-
Lifting plan -Appointed Person and Duty holders- testing/certification - ground conditions - SWL, Temporary Works etc.
-
Recommended Action.
6 Mobile Plant & MEWPs.
-
Fit for purpose - tested/inspected - Anti crush technology- TW pile mat.
-
Recommended Action.
7 Portable Tools.
-
PAT - fit for purpose etc. Reduced voltage, Battery operated.
-
Recommended Action.
8 Access/egress.
-
Adequate - maintained in good order, Pedestrian segregation, barriers and signage in place?
-
Recommended Action.
9 Electricity
-
Inspection/test - isolation/lock off - 110v- permit to work/ Liven up- Competent persons.
-
Recommended Action.
10 Environmental.
-
Waste management plan, WTN/ Consignment Note recorded - spill kit and procedure - noise - dust - mud controls/ suppression etc.
-
Recommended Action.
11 Hoarding/ Fencing/security.
-
Adequate - maintained etc.- Hoarding- temporary works design, inspected?
-
Recommended Action.
12 Subcontractor Management.
-
Co ordinated - supervised, RAMS, Competency,
-
Recommended Action.
13 Personal Protective Equipment.
-
Fit for purpose - Hard Hat, Hi-Viz, Gloves, Safety footwear, Eye protection,RPE,face fit tested.
-
Recommended Action.
14 Edges/openings/stairways- W@H
-
Are all edges Adequately guarded - inc. handrails on stairs, Risers, shafts - Are stairs unobstructed and safe to use?
-
Recommended Action.
15 Site Good Order
-
Housekeeping standards - Is site clean and tidy? slips/trips/falls prevention - suitable lighting etc.
-
Recommended Action.
16 Fire Precautions.
-
Site Fire plan in place - Emergency alarm points on site - Escape signage - Fire extinguishers in place, Tested/inspected - exit routes - Emergency muster point - control of flammable substance etc. compliance with Fire Safety in Construction- JCoP, Fire safety Act and Regulations?
-
Recommended Action.
17 Occupational Health
-
Are suitable Occ health systems and controls in place? Noise - HAVS - MSDs - Dermatitis etc. Occ health monitoring procedures implemented?
-
Recommended Action.
18 Welfare
-
Sufficient facilities in compliance with CDM- adequately equipped - suitably maintained in good order?
-
Recommended Action.
19 First Aid
-
Nearest A&E hospital location detailed on noticeboards - Site first aiders identified - first aid equipment on site.
-
Recommended Action.
20 Competency
-
Site inductions completed? - tool box talks - training. CSCS cards/ certificates checked for Subcontractors?
-
Recommended Action.
21 Documentation
-
Construction Phase Plan - Pre Construction information - statutory notices displayed?
-
Recommended Action.
22 Asbestos.
-
Survey report - management plan/ R+D survey - Removal and disposal RAMS and contractors appointed - licensed work - Asbestos Awareness etc
-
Recommended Action.
23 Safe Systems of Work
-
Subcontractor Method Statements - COSHH - Risk Assessments - Permits etc.
-
Recommended Action.
24 Traffic Management
-
Traffic plan - segregated routes - routes maintained - signage etc.
-
Recommended Action.
25 Temporary Works
-
Designed - co ordinated etc. TW plan and Register- TWC appointed
-
Recommended Action.
26 Worker Engagement & Consultation
-
Arrangements, evidence. Meeting minutes recorded.
-
Recommended Action.
-
Overall Comments:
-
Site Manager Action / Comments:
-
Advisor
-
Actions taken to address shortfalls.
-
Closed Out by and date