Mobile Scaffold Towers
-
Mobile Scaffold Towers
Overview This talk will cover: erection, use, stability and hazards.
Before erecting the tower
1 Check all the components are in good condition.
2 Check wheels for effective rotation.
3 Check brakes and locking devices work correctly.
4 Before erecting a tower on a suspended floor, ensure the bearing capacity of the floor is sufficient for the planned load.
Before use
1 Ensure the tower is vertical and square/
2 Towers must not be used unless the wheels are locked.
3 Check that outriggers are set correctly and secured.
4 Ensure the platform is fully boarded out and guard-rails and toe-boards are fitted if the working platform is over 2 metres high.
5 The gap between toe-boards and mid guard-rails and between mid and top guard-rails must not exceed 470mm.
Stability
1 Never climb up the outside of a tower – use the stairway or ladder on the inside.
2 Follow the manufacturer’s instructions on base to height ratio.
3 Hoist materials up from the inside of the tower.
4 Tie the tower to a permanent structure where possible.
5 Don’t move the tower if people or materials are still on the platform. Don’t pull the tower along while standing on it
Hazards
1 Don’t exceed the manufactures’ SWL for the tower.
2 When moving towers, ensure there are no portholes, obstructions or overhead power lines in the way.
3 When working, ensure the access hatch is closed on the platform.
4 Never use ladders or steps on a scaffold platform as this will cause the tower to turn over.
5 Towers must only be used on firm surfaces. Where the ground is soft, adequate support must be provided. -
Toolbox talk complete?
-
Now go to section "Toolbox talk attendee register"
Toolbox talk attendee register
-
Toolbox talk attendees -
Engineer -
-
Have you fully understood this toolbox talk?
-
Please report to your supervisor to discuss your concerns.
-
Name of engineer -
-
Signature -