Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Cardinal Rules -We will PREPLAN our work and ensure everyone understands required tasks and steps prior to work beginning -We will wear required PPE at all times -We will ensure proper FALL PROTECTION when working at heights greater than 6ft -We will follow appropriate LOCK OUT / TAG OUT procedures -We will follow appropriate ARC FLASH procedures when working near or testing live electrical systems -We will only enter EXCAVATIONS and CONFINED SPACES after we ensure proper planning, testing, communication, equipment, and emergency plans are in place
Ahern Basics
-
Jobsite PrePlan onsite
-
Daily Pre-Task Planning complete
-
Stretch and Flex Program utilized
-
Employees on site understand Ahern's Cardinal Rules
-
Emergency Telephone #'s available and location of nearest medical facility identified
-
Employees have discussed this weeks Toolbox Talk and understand the topic
-
Appropriate PPE utilized for the required task(s) (hardhat, safety glasses, work gloves, respirator, fall protections, etc.)
-
Required number of fire ext. properly located and inspected
-
All vehicles & other mobile equipment provided with fire protection
-
Work area, aisles and passageways clean and organized
-
Employees understand Safety Data Sheets (SDS) and Ahern's 3E 1-800 system
-
Ahern vehicle in good condition (housekeeping concerns, damage to vehicle etc.)
Material Handling
-
Proper lifting techniques, team lifting, mechanical advantage utilized
-
Material stored at appropriate height / distance appropriate to work area
-
Forklift and/or crane inspected and in good condition
-
Qualified personnel involved in the rigging process
-
Equipment load capacities being followed
-
Rigging equipment free from defect
Working at Heights
-
Aerial lifts, ladders, scaffold and other equipment properly inspected and utilized
-
Fall protection discussed prior to work (fall protection plan available when applicable)
-
Fall protection being utilized at heights greater than 6ft
-
Personnel below are protected from falling objects
-
Openings and leading edge work 6 ft or greater equipped with proper barricade, guardrail or cover
Hot Work
-
Flammable and explosive materials stored and handled safely
-
Compressed gas cylinders stored and secured upright
-
Empty gas cylinders marked
-
Cylinders capped when not in use
-
Welding screens provided
-
Equipment in good repair, insulators, grounding, welding leads
-
Adequate ventilation or respirator utilized
Energy Isolation
-
Energy source identified and understood by employees working on system
-
Energy source LO/TO by all employees in the area
-
Is this a multiple energy source system (multi LO/TO permit required)
Electrical
-
Assured Grounding Program up to date
-
Electrical equipment in good condition
-
GFCI Utilized
-
Adequate Arc Flash Protection (I.e. Hazard boundary, permit, customer discussion)
-
Arc Flash Equipment and PPE inspected and in good condition
-
Safe work practices implemented (cords out of pathways, kept out of water, etc.)
Specialty Work
-
Confined Space
-
Employees competent in confined space work
-
Air monitor on site and results documented (ensure proper calibration and maintenance)
-
Adequate ventilation
-
Energy sources locked out
-
Hazards eliminated and reclassified Non-Permit
-
Precautions taken if deemed Permit Required Confined Space (attendant, tripod, etc.)
-
Trenching/Excavating
-
Employees competent in trenching/excavating
-
Was one-call system contacted
-
Protective system properly implemented
-
Surface encumbrances protected/supported
-
Ladder within 25' of all employees
-
Utilities protected/supported
-
Spoil piles minimum of 2' from edge of excavation
Health Hazards
-
Ahern notified of potential exposure and documentation provided
-
Employees understand the hazards and have adequate training / protection
-
Lead based paint abated or safe work practices implemented prior to entry
-
Asbestos abated or encapsulated prior to entry
-
Precautions taken to control silica dust
-
Potentially harmful atmosphere controlled and monitored
Subcontractor Safety
-
Subcontractors following Ahern's policies and procedures
Additional Comments / Observations
Positive Insight "Safety Excellence"
-
Comments
Signature
-
Add signature
-
Add signature