Title Page
-
Site
-
Location of Inspection
-
Prepared by
-
Conducted on
-
Personnel
Requirements
-
Are the latest revision of Jessella Details and Elevation drawings on site and being followed?
-
Are the latest revisions of Rockwool Installation Manuals on site and being followed?
-
Are the latest revisions of Alivas Installation Manuals on site and being followed?
-
Has the Installation Method been read and understood by all operatives?
-
Is the weather being monitored daily?
Substrate
-
Has QA for the SFS & Sheathing Board been completed?
-
Is the area clean and tidy, ready for installation?
-
Have the Cavity Barriers been installed fully, uninterrupted by the Horizontal Barriers?
-
Has any required protection been applied?
Aluminium Flashings
-
Have all flashings been installed line and level as per Jessella drawings?
-
Have the correct fixings been used for the installation?
-
Are the flashings the correct colour/finish and free from damage?
Baserail and Insulation
-
Have the base rails been installed level?
-
Have all corners been mitred?
-
Have base rails been installed using the correct fixings?
-
Have base rails been connected using 'H' connectors?
-
Have insulation boards been cut/rasped correctly?
-
Has the adhesive been applied correctly to the back of the insulation board?
-
Have insulation boards been installed with staggered joints?
-
Have any open joints been filled with a slither of insulation?
-
Have insulation boards been installed with the dense face, facing outwards?
-
Have the insulation boards been installed using the correct fixings following the fixing pattern?
Basecoat
-
Have all beads been installed line and level?
-
Has the basecoat been applied to the correct thickness?
-
Has reinforcing mesh been applied correctly?
-
Does the reinforcing mesh overlap by at least 100mm?
-
Have all stress patches been applied?
-
Have fire pins been installed as required?
-
Has the smoothing coat been applied correctly?
-
Is the finish line and level?
Brickslips
-
Have the brickslips been set out correctly?
-
Have the correct colour brickslips been installed?
-
Has adhesive been applied and trowelled to the wall correctly?
-
Has adhesive been applied and trowelled to back of the brickslip correctly?
-
Have the brickslips been installed line and level using spacers?
-
Were all spacers removed once adhesive had set?
-
Has the area been pointed correctly using the correct mortar?
Site alterations
-
Are there any site alterations?
Drawings
-
Relevant drawings
Comments
-
Are there any comments?
Sign off
-
The below signatures deem all Jessella works mentioned In this report complete to drawings and handed over to RG Group.
-
Checked on behalf of Jessella
-
Checked on behalf of Client