Title Page
-
Client
-
Serial number of charger
-
Charger address
-
Date of commissioning
4.3. Checks before inital startup
-
Mechanical visual inspection
-
Screw connections, tight fit
-
Earthing system
-
Lightning protections for supply lines
-
Selectivity
-
Operating conditions
-
Protection cover
-
Residual current protection device
-
Short circuit resistance
-
Automatic shutdown of the power supply
-
Table 22: Checks to be carried out before commissioning
4.4. Commissioning protocol
Base data:
-
Client
-
Client-Charger-ID (EVSE-ID)
-
Serial number of charger
-
Model
-
Maximum input power available on site(kW)
-
LoadManagement available
-
Manufacturer/Model:
-
Lock cylinder
-
If Client above: description
-
Type of location
-
Charger address
-
GPS-Coordinates
-
Installation company if other than Ísorka
-
Name of Technician
-
Date of commissioning
Existing charging outlets(please tick the box):
-
CCS2 HPC (cooled)
- 1
- 2
- 3
- 4
-
CCS2_400A
- 1
- 2
- 3
- 4
-
CCS2_250A
- 1
- 2
- 3
- 4
-
CCS2_200A
- 1
- 2
- 3
- 4
-
CHAdeMO_200A
-
CHAdeMO_125A
-
GB/T
-
CCS1
-
AC/Typ 2
Check before switching on for the first time:
-
External visual inspection of the charger (damage, defects):
-
Result:
-
Checking the stability:
-
Result:
-
Accessibility of the charging station granted?
-
Result:
-
Inspection of the cable connections
-
Result:
-
Inspection of the fuses
-
Result:
-
Visual inspection of the screw connections (sealing wax present)?
-
Result:
-
Remove and reinsert SIM cards
-
Result:
-
If cooling unit available: Coolant level ok? Correctly connected?
-
Result:
-
Is the inside of the charger clean and free from traces of condensation?
-
Result:
-
Checking the air and creepage distances
-
Result:
-
Checking the filter mats
-
Result:
-
Mains voltages correct?
-
Result:
-
Functional inspection of the electrical protective devices
-
Result:
-
Earthing system complete? Potential equalisation connections continuous?
-
Result:
-
Comments:
Checks when switching on for the first time:
-
Check fan and pump noise (if applicable)
-
Result:
-
Functional check of the RFID reader
-
Result:
-
Checking the function of the screen buttons
-
Result:
-
Checking the function of the screen
-
Result:
-
Functional testing of the LED rings on the connectors
-
Result:
-
Comments:
Charging tests must be carried out for each individual charging point
-
Comments:
Chargepoint 1
-
Peak-Power (kW)
-
Charged energy (kW)
-
Carried out:
-
Result:
Charpoint 2
-
Peak-Power (kW)
-
Charged energy (kW)
-
Carried out:
-
Result:
Chargepoint 3
-
Peak-Power (kW)
-
Charged energy (kW)
-
Carried out:
-
Result:
Chargepoint 4
-
Peak-Power (kW)
-
Charged energy (kW)
-
Carried out:
-
Result:
AC (if available)
-
Peak-Power (kW)
-
Charged energy (kW)
-
Carried out:
-
Result:
The following photos must be inclosed
-
Display door open
-
Display door closed
-
Cable door open
-
Cable door closed
-
Service door open
-
Service door closed
-
Type plate(sticker outside at the bottom of the hypercharger)
-
CRTL_COM with visible connetions
-
Output side of the output switchgear
-
Possibly existing cooling unit(s)
-
Location photo
Test results:
-
We confirm that the charging device complies with the applicable standards
-
According to generally recognised technical rules, the safe use of the loading equipment is guaranteed when used as intended
Date and signature
-
Date of commissioning
-
Signature