Title Page

  • Client

  • Serial number of charger

  • Charger address

  • Date of commissioning

4.3. Checks before inital startup

  • Mechanical visual inspection

    hyc commissioning check before startup I.png
  • Screw connections, tight fit

    hyc commissioning check before startup II.png
  • Earthing system

    hyc commissioning check before startup III.png
  • Lightning protections for supply lines

    hyc commissioning check before startup IV.png
  • Selectivity

    hyc commissioning check before startup V.png
  • Operating conditions

    hyc commissioning check before startup VI.png
  • Protection cover

    hyc commissioning check before startup VII.png
  • Residual current protection device

    hyc commissioning check before startup VIII.png
  • Short circuit resistance

    hyc commissioning check before startup VIIII.png
  • Automatic shutdown of the power supply

    hyc commissioning check before startup X.png
  • Table 22: Checks to be carried out before commissioning

4.4. Commissioning protocol

Base data:

  • Client

  • Client-Charger-ID (EVSE-ID)

  • Serial number of charger

  • Model

  • Maximum input power available on site(kW)

  • LoadManagement available

  • Manufacturer/Model:

  • Lock cylinder

  • If Client above: description

  • Type of location

  • Charger address

  • GPS-Coordinates
  • Installation company if other than Ísorka

  • Name of Technician

  • Date of commissioning

Existing charging outlets(please tick the box):

  • CCS2 HPC (cooled)

  • CCS2_400A

  • CCS2_250A

  • CCS2_200A

  • CHAdeMO_200A

  • CHAdeMO_125A

  • GB/T

  • CCS1

  • AC/Typ 2

Check before switching on for the first time:

  • External visual inspection of the charger (damage, defects):

  • Result:

  • Checking the stability:

  • Result:

  • Accessibility of the charging station granted?

  • Result:

  • Inspection of the cable connections

  • Result:

  • Inspection of the fuses

  • Result:

  • Visual inspection of the screw connections (sealing wax present)?

  • Result:

  • Remove and reinsert SIM cards

  • Result:

  • If cooling unit available: Coolant level ok? Correctly connected?

  • Result:

  • Is the inside of the charger clean and free from traces of condensation?

  • Result:

  • Checking the air and creepage distances

  • Result:

  • Checking the filter mats

  • Result:

  • Mains voltages correct?

  • Result:

  • Functional inspection of the electrical protective devices

  • Result:

  • Earthing system complete? Potential equalisation connections continuous?

  • Result:

  • Comments:

Checks when switching on for the first time:

  • Check fan and pump noise (if applicable)

  • Result:

  • Functional check of the RFID reader

  • Result:

  • Checking the function of the screen buttons

  • Result:

  • Checking the function of the screen

  • Result:

  • Functional testing of the LED rings on the connectors

  • Result:

  • Comments:

Charging tests must be carried out for each individual charging point

  • Comments:

Chargepoint 1

  • Peak-Power (kW)

  • Charged energy (kW)

  • Carried out:

  • Result:

Charpoint 2

  • Peak-Power (kW)

  • Charged energy (kW)

  • Carried out:

  • Result:

Chargepoint 3

  • Peak-Power (kW)

  • Charged energy (kW)

  • Carried out:

  • Result:

Chargepoint 4

  • Peak-Power (kW)

  • Charged energy (kW)

  • Carried out:

  • Result:

AC (if available)

  • Peak-Power (kW)

  • Charged energy (kW)

  • Carried out:

  • Result:

The following photos must be inclosed

  • Display door open

  • Display door closed

  • Cable door open

  • Cable door closed

  • Service door open

  • Service door closed

  • Type plate(sticker outside at the bottom of the hypercharger)

  • CRTL_COM with visible connetions

  • Output side of the output switchgear

  • Possibly existing cooling unit(s)

  • Location photo

Test results:

  • We confirm that the charging device complies with the applicable standards

  • According to generally recognised technical rules, the safe use of the loading equipment is guaranteed when used as intended

Date and signature

  • Date of commissioning

  • Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.