Observation Log Information

  • Project: AMD Block 3, Sunnyvale, CA

  • System: Below Grade Combined - Elevator Pits, Podium Perimeter Wall Substrate, Podium Perimeter Wall Membrane, Waterstop

  • Log Number

  • Conducted on:

  • Weather

  • Time On-Site

  • Time Off-Site

  • Hours On-Site

  • Reported by

  • Reported to: Jeff Troy- The Irvine Company, CETCO Field Services

  • Warranty Number: W-10495

  • Present at site

  • Location:

Checklist

Elevator Pits

  • Elevator Pits

  • 1. Waterproofing sheets installed with 4" laps at edges, end laps staggered minimum 12" per manufacturer's recommendations.<br>

  • 2. Staples installed at all laps.

  • 3. Trowel grade below grade mastic applied around elevator plunger sleeve.

  • 4. Water stop applied around elevator plunger cylinder, set in a bead of Cetseal and secured with tie wire.

  • 5. Water stop applied around top of perimeter of elevator pit walls below topping slab, roll ends butted tightly together.

Podium Perimeter Wall Substrate

  • Podium Perimeter Wall Substrate

  • 1. Concrete Wall reviewed for voids, projections and surface irregularities

  • 2. Surface irregularities repaired

  • 3. Surface free of dirt, dust, oil, grease, cement lattice or any other foreign material

  • 4. Voids and honeycombing repaired with trowel grade below grade mastic.

  • 5. Form ties filled with non-shrink grout and capped with trowel grade below grade mastic

Podium-Perimeter Wall Membrane

  • Podium-Perimeter Wall Membrane

  • 1. Surface is ready for waterproofing application.

  • 2. Below grade mastic applied at vertical inside corners

  • 3. Sheets typically installed horizontally, lapped 4" minimum, end laps staggered 12"

  • 4. Waterproofing sheets terminated below finish grade elevation and secured with fasteners (verify fastener spacing).

  • 5. Penetration flashed and sealed.

  • 6. Seam tape applied at seams.

  • 7. Self-adhered flashing sheet installed over primed substrate, lapped over top of edge of below grade sheets and terminated.

  • 8. Protection course or drain mat installed.

  • 9. Tooled bead of below grade sealant applied around all penetrations and exposed laps of the self-adhered flashing sheet.

  • 10. 60 mils of liquid applied waterproofing has been installed at the CMU walls.

  • 11. Self-adhered membrane, 40 mil, 12" wide has been installed and centered over the metal framing to podium slab transition. WRB in shingled under

  • 12. At liner unit corner transitions, a 9" wide strip of 705FR SAM is installed and centered over the CMU Wall to metal framing joint.

  • 13. 705 FR SAM has been installed at all inside/outside corners extending a min. of 3" on each side prior to the 60 mils of liquid applied membrane being installed.

  • 14. At CMU to metal stud transitions, a 9" wide strip of 705 FR SAM is installed and centered over the CMU wall to metal stud framing joint.

Waterstop

  • Waterstop

  • Surface is ready for Waterstop application.

  • Release paper removed and Waterstop set in a bead of below grade sealant.

  • Waterstop is set a minimum of 3" from the edge of concrete.

  • 4. Coil ends are butted tightly to form one continuous Waterstop. Do not overlap butt ends.

  • *** The items contained within this box correlate to the checklist published on the Irvine Company Quality Control portal and are listed here for our convenience of data entry within that system only. In no way is this list to be construed as an all-inclusive list of work performed by Architectural Testing, Inc. Note slight modifications were made to list for Roof Verification Letter only to be project specific.

Work In Progress

  • What work is occurring on-site?

Trade Contractor Issues

  • Drywall

  • Finish Carpenter

  • Framing

  • Gutters & Downspouts

  • Hardrock

  • Iron Work Ornamental

  • Lath/Plaster

  • Plumbing

  • Private Deck Coating

  • Roofing

  • Sheet Metal

  • Stair Fabricator

  • Waterproofer

  • Weatherstripping

  • Windows/Sliding Doors

  • Other

  • Superintendent

  • Work in Progress

Observations

Elevator Pits

  • Elevator Pits

  • The finished sub-grade surface was observed well-leveled, uniform, free of debris and standing water.

  • Coreflex is loosely laid with the yellow PVC layer facing down, with minimum 4 inch overlaps. Coreflex extends a minimum of 24 inches beyond the edge of the elevator pit.

  • Prior to hot air welding, test welds with minimum 1 1/2 inch welds were taken to ensure that the equipment is calibrated. Welding equipment is run off of its own power supply.

  • During hot air welding, seams were wiped clean and free of dust, debris and water. Welds were observed to be 1 1/2 inches. Where membrane edges for a "T", 4 inch diameter "T" patches were welded at the corners extending the thermoplastic membrane of the Coreflex in each direction of the "T".

  • At welded seams, Coretex is installed over the seam, set in Cetseal sealant lapping a minimum of 4 inches on each side of the seam. The Cortex is welded to the Coreflex. .

  • Where Coreflex transitions to Liquid Boot, Coreflex is encapsulated in Liquid Boot a minimum of 6 inches.

  • Other

Perimeter Wall Substrate/Membrane Install or CMU Elevator Walls

  • Perimeter Wall Substrate/Membrane Install or CMU Elevator Walls

  • The CMU/Concrete wall was inspected prior to the installation of Swelltite. Substrate is smooth and free of voids. Any voids or rough patches have been covered with Bentoseal or M-2000. The substrate is adequate for Swelltite installation.

  • Bentoseal was installed along the footing to CMU wall transition and along inside corners of the CMU wall. Primer was applied to the CMU wall and a 12 inch side strip sheet of Swelltite was installed along the footing to CMU wall transition, extending 6 inches onto the footing and 6 inches up the CMU wall. At inside corners and outside corners, a 20 inch strip sheet of Swelltite was installed, extending 10 inches in each direction. Cetseal sealant is applied over fasteners along the footing.

  • At saw cut control joints, Cetseal was added to the control joint and a 20 inch piece of Envirosheet was applied and centered over the saw cut joint. Swelltite was then applied and centered over the previously applied Envirosheet.

  • Temporary termination (termination bar or Envirosheet) has been installed to protect work that has not been completed.

  • Termination bar was installed at the edge of the Swelltite along the footing and fastened at 12 inches O.C. Cetseal was installed over the termination bar and tooled smooth.

  • Aquadrain 100BD was installed over the Swelltite along the horizontal at the footing. Aquadrain 15XP is installed over Swelltite butting up against the Aquadrain 100BD. A general purpose spray adhesive was used to adhere the Aquadrain 100BD to the previous installed Swelltite. Fasteners and used to hold up the drainboard and covered with Cetseal sealant.

  • Aquadrain 15XP was installed over the Swelltite along the horizontal and vertical. Termination bar was installed at the top of the Aquadrain 15XP and fastened at 12 inches O.C. A cant of Cetseal was installed along the top of the termination bar and tooled smooth.

  • ATI advises that backfill and compaction to 85% Modified Proctor occur immediately after the completed installation of the Swelltite and Aquadrain 15XP.

  • Other

Waterstop

  • Waterstop

  • Waterstop has been installed as shown on the plans. Waterstop is set in sealant with ends butting up against each other.

  • Waterstop is installed allowing for a minimum of 3 inches of coverage between the Waterstop and the edge of the wall/slab

  • Other

Additional Notes

  • Items marked as N/A on the check list above do not apply at the time of the inspection or are not applicable to the system being installed for this project.

  • For Podium Perimeter Wall Substrate:

  • Initial inspection?

  • Follow-up required?

  • For Elevator Pits:

  • Initial inspection?

  • Follow-up required?

  • For Podium-Perimeter Wall Membrane:

  • Initial inspection?

  • Follow-up required?

  • For Waterstop:

  • Initial inspection?

  • Follow-up required?

  • undefined

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.