Information

  • Wet area Pre-Sheet ITP

  • Site Address

  • Area being inspected.

  • Plumber - Ben Edmunds Plumbing

  • Electrician - E4 Electrical

  • Mechanical Contractor - Ben Rafferty

  • Date and Time of Inspection

  • Prepared by (Full Name)

Hydraulic

  • All bath, basins, WC cisterns and shower tap locations per the drawings

  • Outlets set at correct depth for tile thickness?

  • Hydraulic pipework rough-in completed and tested?

  • Basin, Bath and WC waste outlets in the correct location and capped?

  • All floor wastes placed as per the drawings?

  • All pipework through timber/steel frame siliconed at penetrations?

  • Is the water pipework pressure test conducted?

  • Materials used are approved and appropriately sized?

  • Hot to the left and Cold to the right?

  • Tempering valves installed? Bathroom fixtures reach a maximum of 50 degrees centigrade?

  • Pipe work is labelled appropriately?

  • Securing pipe work (poly pipe work) at every stud or 600mm max on horizontal?

  • Waste pipework acoustically insulated

Completion

  • Inspection Result

  • Recommendations

  • Additional Photos

  • Contractor's ITP Received?

  • Full Name and Signature of Site Manager

  • Full Name and Signature of Contractor

Electrical

  • Visual check of power and lighting cables

  • Switches and GPO's at correct height?

  • Provisions made for wall & ceiling lights and joinery lighting.

  • Power and control for UFH including conduits for heat-matt tails and floor probe.

  • Ceiling plan as per RCP

  • Power and control for heated towel rail?

  • Power run to exhaust fan location?

Completion

  • Inspection Result

  • Recommendations

  • Additional Photos

  • Contractor's ITP Received?

  • Full Name and Signature of Site Manager

  • Full Name and Signature of Contractor

Mechanical

  • Mechanical Exhaust Fans Installed

  • Control wiring installed

  • Exhaust air ductwork installed to external grille location

  • Penetrations for Grilles set-out and created

  • FCU Mounted securely

  • AC Ductwork installed including sealing of joints and duct work is not crushed anywhere

  • Fresh air duct installed

  • FCU filter and control box accessible

  • Condense pipe work installed in accordance with Australian Standards to tundish

Completion

  • Inspection Result

  • Recommendations

  • Additional Photos

  • Contractor's ITP Received?

  • Full Name and Signature of Site Manager

  • Full Name and Signature of Contractor

General

  • Wall framing set-out correctly?

  • Door jamb/Cavity sliding door installed plumb and flush with wall frame?

  • Bathroom entry stepdown flush with frame.

  • Niches and built-in joinery openings formed?

  • Blocking for all wet area accessories

  • Blocking for Vanity/ Basin

  • Blocking for mirror cabinet

  • Blocking for heated towel rail

Completion

  • Inspection Result

  • Recommendations

  • Additional Photos

  • Full Name and Signature of Site Manager

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.