Check Cabinet Lights, fabric and all displays are operational
-
List fixture ID and isseus
-
Check All Drainage are free from leaks
-
List any Fixtures that are leaking
-
Is the drainage Pumped or Gravity
-
Pump Trays Must Be 1 For Every 3 Cases.
-
Visual Check Of Chiller Coldstore/lights/Fabric
-
Visual Check Of Freezer Coldstore/Lights/Fabric
-
Check And Test All Entrapment Alarms (coldstores)
-
Check Coldstore Door Switches Work/Door Heater
-
Check Pack(s) Front Lable Is Correct Information
-
Refrigerant Lable Is Correct ?
-
Refrigerant Charge Is Correct ?
-
All Pipe Work Is Labbled Clearly And Correct ?
-
Visual Check Of All Electrics Inside Pack Pannel
-
Visual Check Of Compressors H/P,L/P & Oil Level
-
Visual Check Oil Separator (Level %)
-
Visual Check Of Liquid Level Receiver %
-
All PRV'S Fitted And Tagged Suction/Liquid/discharge
-
All Identification Lables Fitted And Correct ?
-
Visual Check Off Condenser Fans Working
-
Visual Check Off All Air/Con Indoor Units
-
Visual Check Off All Air/Con Outdoor Units
-
Check For any Alarms On A/C Remote Controllers
-
Check A/C Pipe Work Is Labbled Correctly
-
Check Front End Pannel (RDM) Any Alarms
-
Check Front End Pannel (RDM) Alarm History
-
Check If There Is Any Remote Leak Detectors Fitted
-
Check Site Layout Drawing Is Fitted And Correct ?
-
Check Dial out Test Has Been Done
-
Check All O+M Mannuals Are Updated And Correct ?
-
Please insure all cases/coldstores/pacs/condensers/air conditioning units ect.. Are all fitted with asset stickers and uploaded to the office.
-
If you have any queries about anything regarding the hand over please speak to a senior team member who will assist you with your questions.
Sign Off
-
Contractor
-
Arcus
-
Store