Information
-
Audit Title
-
Client / Site
-
Date and time of arrival
-
Conducted on
-
Prepared by
-
Location
-
Document No.
-
Personnel
-
THE FOLLOWING SECTION MUST BE COMPLETED AND CONSIDERED SATISFACTORY BEFORE CONTINUING FURTHER WITH THIS AUDIT
Preliminary requirements
-
Is there a valid (i.e. in date) ASB5 notification form on site for the works to be audited?
-
Is there (or will there be) asbestos removal work or cleaning in progress within the enclosure during the audit?
-
Is there provision to observe work practices within the enclosure by means of CCTV and/or viewing panel(s)?
-
Is there a site specific Plan of Work available on site for the works?
-
Is there a copy of the company standard procedures/ generic procedures available on site?
-
Is the decontamination unit fully functional in terms of power, ventilation, and the provision of hot and cold running water for showering?
-
DO NOT PROCEED WITH THE AUDIT UNLESS EACH RESPONSE ABOVE IS AFFIRMATIVE. SHOULD ANYTHING ABOVE BE AMISS THAT CAN BE RECTIFIED IMMEDIATELY, THEN CONTINUE WITH THE AUDIT ONCE RECTIFIED.
-
SHOULD ANYTHING ABOVE BE AMISS THAT CANNOT BE RECTIFIED IMMEDIATELY, THEN INFORM THE SUPERVISOR, THAT THE AUDIT CANNOT CONTINUE
ASB5 Notification Form
-
Are details of any other licence holders recorded in section 3 of the ASB5?
-
What form of asbestos containing material is being worked upon? (Section 4 of ASB5?)
-
What is the approximate extent of the works stated in section 5 of the ASB5?
-
What is the maximum number of employees per shift stated in section 5 of the ASB5?
-
How many operatives (including the supervisor) are on site?
Site documentation
-
Is the contract supervisor the same person as specified in the plan of work?
-
Does the plan of work detail to whom upon? (Section 4 of ASB5)
-
Does the plan of work detail when the work is to be carried out? (Including start/finish times and weekend variations)
-
Does the plan of work detail the analytical company providing the 4 stage clearance?
-
Does the plan of work detail who the analytical company is contracted to?
-
Does the plan of work detail the type of asbestos involved? (i.e. Amosite, Chrysotile, Crocidilite)
-
Does the plan of work detail the condition of the asbestos containing material to be removed? (e.g. good, fair or poor)
-
Does the plan of work (or standard procedures) detail who is authorised to amend the plan of work?
-
Does the plan of work (or standard procedures) detail the construction method for enclosures and air locks?
-
Does the plan of work (or standard procedures) detail the arrangements for smoke testing and witnessing? If Yes, please record name/title of proposed witness
-
Does the plan of work (or standard procedures) detail decontamination entry and exit procedures?
-
Does the plan of work (or standard procedures) detail the type of respirators used?
-
Does the plan of work detail the asbestos removal technique to be used?
-
Does the plan of work detail the air monitoring arrangements for the duration of the works?
-
Are welfare facilities detailed in the plan of work and are they available for use as described?
-
Is the scope of works adequately described on the plan of work, and does it match the details recorded on the ASB5?
-
Is there a site specific risk assessment available for inspection, for hazards other than asbestos? e.g. hot work, work at heights, use of hand tools, confined spaces, electricity, manual handling etc
-
Is there a set of COSHH assessments on site? (smoke, fluid, foam, spray adhesive etc). NB. Material safety data sheets on their own are insufficient
-
Is there a copy of the contractor's current valid licence available for inspection?
-
Is there documented evidence on site confirming current insurance cover for both employers liability and public liability? e.g. Insurance schedule
-
Are daily site and plant inspection records (including DCU, enclosure, airlocks, NPU's & vacuum cleaners) available for inspection and up to date?
-
Does the NPU inspection record include manometer/ pressure gauge readings for each NPU in use (including DCU)?
-
Has the smoke test record for the enclosure been completed and do the witness details match those stated in the plan of work?
Site Supervisor and/or Operative(s)
-
Current medical certificate
-
Current training certificate?
-
Training provider
-
Face fit test certificate for RPE in use?
-
Examination record for RPE in use? (daily if in enclosure, currently monthly if not)
-
Adequate response when questioned regarding emergency procedures? (if not in enclosure)
-
Supervisor/operative(s) clean shaven?
-
If out of enclosure, or if seen before entry
-
Additional comments
-
Are all copies of certificates (above) individually authenticated by, or under the direction of, senior management, with a statement confirming their validity?
Site Organisation
-
Does the sketch plan included with the plan of work match the site set up, and include the positions of the NPU, airlock, bag lock (if applicable), viewing panels/ CCTV and DCU as a minimum?
-
Do viewing panels and/or CCTV show all areas so far as is reasonably practicable?
-
Is each viewing panel (where applicable) at least 600 x 300mm
-
Are there adequate warning signs which comply with the safety signs and signals regulations? (including the black hand prohibition symbol)
-
Is there a suitably stocked first aid kit available on site?
Plant on site/ Certification
-
Are there at least 2 H-type vacuum cleaners on site?
-
Is there an electrical safety certification for DCU?
-
Is there a current gas safe certification for the DCU? (LPG)
-
Are current DOP test certificates (or copies) available and relevant to each vacuum on site?
-
Does the number and capacity of the NPUs in use correspond with that stated in the plan of work?
-
Is there a current DOP test certificate (or copy) available on site for the NPU within the dirty end of the DCU?
Enclosure/ Airlock
-
Is the enclosure in sound condition and constructed so as to prevent the spread of asbestos?
-
Is the airlock free from visible asbestos debris?
-
Is a bucket and sponge (or similar) available for decontamination or respirator?
-
Are the airlock openings either oval or rectangular in shape?
-
Do the flaps cover the airlock adequately?
-
Are all of the airlocks flaps weighed?
-
Is each stage of the airlock at least 1m x 1m x 2m (height)?
-
Does the inner stage of the airlock have a viewing panel at least 600 x 300mm?
Air extraction equipment
-
Is the extract sited in the relation to ideal air management?
-
Is the extract capable of giving a minimum of 8 air changes per hour?
-
Is the extract vented to the outside atmosphere where practical?
-
Does each NPU have a non-return flap on the exhaust side of the HEPA filter?
Observed work practices
-
Is the pre filter (or roving head) the only part of the NPU that is exposed to the working area? (i.e NPU sheeted out if inside the enclosure)
-
Does the RPE (including filter) being use match that stated in the plan of work?
-
Are all components of the full face RPE uniquely identifiable? (e.g. mask, blower and battery identified/marked/tagged with name or item/serial number
-
Are colours of coveralls as stated in the plan of work or standard procedure
-
Are all items of necessary PPE being worn properly? (e.g. overall hood over head straps, overalls not tucked in to working footwear etc.)
-
Is the dust suppression method suitable for the type of work or material? (if needle injection machine being used, please state manufacturer)
-
Does the asbestos removal technique being used match that stated in the plan of work?
-
Has the waste been appropriately bagged? (e.g. immediately, and single bagged if still in the enclosure)
Hygiene Facility
-
Is the unit positioned in relation to the work area as stated in the plan of works
-
If the unit is not directly connected to the enclosure, would it of been reasonably practicable to do so
-
Is the transit route as short as possible and away from occupied areas
-
In addition to item 1.6 above, is the unit fully functional/ in working order? (Heating, lighting, water filter, drains etc)
-
Are the internal doors and external door to the dirty end self-closing?
-
Are there an adequate number of shower heads for operatives? i.e. at least 1 for every 4 operatives)
-
Is there a nail brush provided in the shower area?
-
Is the unit in good condition and clean so far as reasonably practicable?
-
Is there a clearance test certificate, from the previous job, for the dirty and shower compartments of the hygiene unit?
-
Are the clean and dirty end doors marked (including prohibited entry and mandatory PPE signage, where required)?
-
Are towels provided?
Waste
-
Are the waste disposal arrangements as described in the plan of work?
-
Has a separate bag lock been provided? If no, state reasons why. If no baglock, is this justified in the plan of work?
-
Is the stage of the baglock at least 1m x 1m x 2m high? If no, state reasons why. If smaller, is this justified in the plan of work?
-
Does the inner stage of the baglock have a viewing panel at least 600 x 300mm? If no, state reasons why
-
Is the baglock free from visible asbestos debris?
-
Is the waste transit route free from residual or split waste?
-
Where applicable, is there sufficient means to separate waste from equipment/ supplies within the company vehicle?
Miscellaneous
-
Are disposable working coveralls and transits coveralls category 3, type 5/6
-
Are contractors vans reasonably tidy and with minimal risk of the spread of asbestos?
Scaffolding
-
Are the asbestos removal contractors using scaffolding on site?
-
Was a sub-contractor used to erect the scaffolding
-
Was the scaffolding liable to disturb asbestos while being erected?
Further comments/ clarifications
-
COMPLETE A SITE AUDIT SUMMARY OF OBSERVATIONS AND/OR RECOMMENDED ACTIONS. IF NO FURTHER ACTIONS ARE REQUIRED, COMPLETE A SUMMARY SHEET WITH A STATEMENT TO THAT EFFECT
-
Add signature