Title Page
-
Conducted on
-
Prepared by
-
Location
Heat Pump Wiring
-
Is the correct size breaker used for heat pump?
-
Is an isolation switch installed for the heat pump and mounted on a fixed structure out beside the heat pump?
-
Is the correct size power supply cable used for heat pump?
-
Is the correct communication cable installed and wired unto correct terminals?
Cylinder Wiring
-
Is the correct sized breaker used for controller on cylinder?
-
Is an isolation switch installed for controller and mounted on a fixed structure beside controller?
-
Is the correct size power supply cable used for controller on cylinder?
-
Is the correct communication cable installed and wired into correct terminals?
-
Is the flow switch switch wired back into correct terminal on control panel?
Heating Controls / Stats Wiring
-
Is each zone/floor corresponding with the correct zone valve?
-
Are all heating controls powered from controller on cylinder?
-
Are all heating controls wired & working?
Heat Pump Mounting
-
Is the unit installed the correct distance from nearest boundaries?
-
Is the unit secured correctly to antivibration mounts via rubber mounts?
-
Is the unit mounted plumb level?
-
Is a condensate drain kit fitted (drain kit located inside HP access door)?
-
If the unit is mounted on wall brackets; is a drip tray installed?
Heat Pump Plumbing (Outdoor)
-
Is the correct size pipework used?
-
Are flexible antivibration hoses fitted and washers used?
-
Are heat pump isolation valves fitted out at the heat pump?
-
Is the flow and return pipework connected correctly?
-
Is the primary flow pipework insulated?
Cylinder Plumbing (Indoor)
-
Is the flow switch installed on the primary pipework and fitted in the correct orientation?
-
Is the flow switch installed on the primary horizontal pipework with 150mm pipework each side free of a bend or appliance?
-
Is flow and return pipework connected the right way around?
-
Is the heating expansion vessel correctly sized, secured and charged to to the correct pressure?
-
Are all pump valves and isolation valves fully open?
-
Has system been completely flushed of air and charged to the correct operating pressure of 2 bar?
-
Are all safety valves and tundish drained through a metal pipe to an appropriate drain point?
Radiator / UFH Plumbing
-
Has all air been removed from emitters?
-
Have all emitters been balanced correctly?
-
If UFH is installed, have the correct flow rates been set?
-
If UFH is installed, are all valves on manifolds / pumps fully open?
Additional ASHP Checklist
-
Unit clearances are correct?
-
Anti-freeze valves fitted or glycol installed in the system?
-
All pipework in cylinder cupboard insulated?
-
Isolation valve fitted on cold inlet?
-
Inlet control group valve fitted in incoming cold with 3m of cylinder?
-
D1 size (max 600mm away from temperature relief valve)?
-
D2 pipework minimum 300mm before the 1st bend?
-
Potable expansion vessel fitted on cold feed between inlet valve and cylinder?
-
Expansion vessel on heating (check pressure is the same on PRV - 3 bar)?
-
Flow switch must be installed in horizontal pipework, allowing a minimum of 150mm horizontal pipework on each side of the flow switch?
-
Lever valves fitted?
-
Hot water outlet starts in 22mm pipe - can be reduced?
Installation Photographs / Commissioning Documentation
-
Add media
Sign Off
-
Add signature
-
Select date