ISO9001:2015 - 8.4 - Control of externally provided processes, products and services - Compliance ISO45001:2018 - 8.1.4 - Procurement - Compliance
Tick here to show procedure(s)/standard(s) have been read
-
IMSQMSLLPP001 [Purchasing]
-
Explain why the procedure has not been read for this audit?
-
IMSQMSLLTP003 [Requesting NDT Services]
-
Explain why the procedure has not been read for this audit?
-
IMSQMSLLQA005 [Assessment of suppliers & subcontractors]
-
Explain why the procedure has not been read for this audit?
-
IMSHMSLLPR008 [Control of Contractors]
-
Explain why the procedure has not been read for this audit?
-
IMSHMSLLTP041 [CoSHH Purchasing Guide]
-
Explain why the procedure has not been read for this audit?
-
ISO 9001 Section 8.4 - Control of externally provided processes, products and services
-
Explain why the procedure has not been read for this audit?
-
ISO 45001 Section 8.1.4 - Procurement
-
Explain why the procedure has not been read for this audit?
VERIFY procedure compliance with requirements within ISO 9001 / ISO 45001 standards
-
Do the procedures sufficiently detail the controls to be applied to external providers (suppliers/sub-contractors)
-
Do the procedures sufficiently detail the requirements to identify hazards and risk for contractors with regards to OH&S requirements
-
Do the procedures sufficiently detail the criteria for evaluation and selection of external providers?
-
Do the procedures sufficiently define and apply OH&S criteria for the selection of contractors?
-
Do the procedures sufficiently define the type and degree of control to be applied to outsourced functions and processes relating to OH&S compliance matters. This must include ensuring arrangements are consistent with legal requirements (i.e. LOLER inspection, compressed air system servicing etc.)
-
Do the procedures sufficiently detail the criteria for monitoring and performance evaluation of external providers?
interview
- Interview 2 purchasers (include one from each facility)
-
Name, title and facility/location of interviewee
-
Ask purchaser how bids (not suppliers) are assessed to determine which supplier to use for the order
-
Ask purchaser how suppliers (nod bids) are assessed and verified on the approved vendor list (AVL)
-
Ask purchaser how poor suppliers are discussed and how suppliers who are unacceptable for orders are communicated
-
Ask purchaser how orders are authorised and when line managers are required to approve purchase orders
-
Auditee Signature
Compliance Checks
CHECK purchase orders for correct content i.e. size, thickness, quantity, origin restrictions, client specific requirements, OH&S controls, legal requirements etc.
-
5 random purchase orders within last quarter; including at least one CoSHH item purchase and one subcontracted activity.
CHECK suppliers were adequately assessed and, as necessary, periodically reviewed before purchase orders were placed
-
5 random suppliers from purchase orders placed within last quarter; Include at least one new supplier where possible; Include at least one quality critical supplier.
-
3 random suppliers from purchase orders placed for Sellafield projects withing the last financial year; Verify kick-off meetings were held and recorded for critical suppliers [see SLM 4.06.02]
CHECK material purchase orders for correct material specification determination
-
5 random purchase orders within the last quarter.
CHECK purchase orders for revision status and revised orders are sent to suppliers
-
Last 2 amended orders
CHECK supplier feedback and trend analysis is discussed at management review meetings
-
Last 2 management meetings
CHECK orders are associated with the correct job numbers (where applicable)
-
5 random purchase orders within the last quarter.
CHECK authorisation levels are current and up to date for organisation structure.
-
Check current list is consistent with management level authorisations
CHECK purchase orders relating to Sellafield projects have been ordered against SLM 4.06.02 requirements, including flow-down requirements to suppliers/sub-contractors
-
3 random purchase orders for Sellafield projects
Final Sign off
Final acceptance
-
Auditor signature