Information
-
Document No.
-
F-M Site
-
Conducted on
-
Prepared by
-
Location
Monday
Monday
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
Fast Response Meeting
-
Time of meeting
-
Managers participation?
-
Focus on solution?
-
Hot topics:
Back on Track
-
Time of review
QRQC
-
Time of review
-
QRQC board updated?
-
QRQC discipline - step by step?
-
QRQC closed < 1 month?
-
Managers participation?
-
Minimum 1 representative per department?
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
5S
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Cleanliness/ organization OK?
-
Is there a standard?
-
Is there an action plan?
Shift Change
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of change
-
Which shifts?
-
No loss during shift change?
-
Operators acknowledge shift change procedure?
Tuesday
Tuesday
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
Fast Response Meeting
-
Time of meeting
-
Managers participation?
-
Focus on solution?
-
Hot topics:
Back on Track
-
Time of review
QRQC
-
Time of review
-
QRQC board updated?
-
QRQC discipline - step by step?
-
QRQC closed < 1 month?
-
Managers participation?
-
Minimum 1 representative per department?
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
5S
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Cleanliness/ organization OK?
-
Is there a standard?
-
Is there an action plan?
Shift Change
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of change
-
Which shifts?
-
No loss during shift change?
-
Operators acknowledge shift change procedure?
Wednesday
Wednesday
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
Fast Response Meeting
-
Time of meeting
-
Managers participation?
-
Focus on solution?
-
Hot topics:
Back on Track
-
Time of review
QRQC
-
Time of review
-
QRQC board updated?
-
QRQC discipline - step by step?
-
QRQC closed < 1 month?
-
Managers participation?
-
Minimum 1 representative per department?
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
5S
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Cleanliness/ organization OK?
-
Is there a standard?
-
Is there an action plan?
Shift Change
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of change
-
Which shifts?
-
No loss during shift change?
-
Operators acknowledge shift change procedure?
Thursday
Thursday
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
Fast Response Meeting
-
Time of meeting
-
Managers participation?
-
Focus on solution?
-
Hot topics:
Back on Track
-
Time of review
QRQC
-
Time of review
-
QRQC board updated?
-
QRQC discipline - step by step?
-
QRQC closed < 1 month?
-
Managers participation?
-
Minimum 1 representative per department?
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
5S
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Cleanliness/ organization OK?
-
Is there a standard?
-
Is there an action plan?
Shift Change
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of change
-
Which shifts?
-
No loss during shift change?
-
Operators acknowledge shift change procedure?
Friday
Friday
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
Fast Response Meeting
-
Time of meeting
-
Managers participation?
-
Focus on solution?
-
Hot topics:
Back on Track
-
Time of review
QRQC
-
Time of review
-
QRQC board updated?
-
QRQC discipline - step by step?
-
QRQC closed < 1 month?
-
Managers participation?
-
Minimum 1 representative per department?
Production Board
-
Which production area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Is bottleneck identified?
-
Is there a buffer before the bottleneck?
-
Is cycle time measured and inside target?
-
Is hourly follow-up filled in?
-
Has the coordinator signed the board?
-
Is operator working 100% of the time?
-
Is there a PPS sheet opened for the biggest loss (<1wk)?
-
Is there reaction/ escalation?
5S
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of audit
-
Cleanliness/ organization OK?
-
Is there a standard?
-
Is there an action plan?
Shift Change
-
Which area?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
Time of change
-
Which shifts?
-
No loss during shift change?
-
Operators acknowledge shift change procedure?
Weekly Activities
MPS
-
When?
-
Was it prepared in advance?
-
Did we meet previous MPS?
-
Do we meet customer demands?
-
Is workforce well dimensioned/ distributed?
Back on Track
-
When?
Changeover
-
Where?
- Foundry - ECA
- Foundry - Tucson
- Foundry - MLDB
- GL#1
- GL#2
- GL#3
- DL#1
- Skirt Coating
- Hard Anodising
- Auto Final Inspection
- Manual Final Inspection
- Cams
- External
- Offices
-
When?
-
Which P/Ns?
-
Is there a changeover plan?
-
Was there external preparation?
-
Did the changeover time match the plan?
Weekly Flash
-
When?
-
Managers participation?
-
Focus on "back on track"?
-
Hot topics: