Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • SWMS and ESC in place, signed off and understood by all

  • Documentation stating formwork design and verification has been approved by the project verifier in accordance with Hold Point B 80.5 (tap this panel and enter

  • HP Released by:

  • Documentation stating the test panel has been approved by the verifier in accordance with hold point B80.5.32

  • HP Released by:

  • Has the pour area been blinded as per design drawings?

  • Pour area set out as per design drawings?

  • Formwork and pour area clean and free of foreign materials

  • Formwork interior surface is treated/sprayed with compliant product (e.g. Wax product)

  • Formwork joints are mortar tight, formwork is secure and constructed according to requirements

  • Survey control for the formwork is within tolerances stated in table B80.11 (verify pour level marks are at correct location and levels)

  • Reinforcement cleaned of foreign materials and conforming to AS/NZS 4671 & tolerances specified in B80.6.9

  • Inspect & verify cast in type & location in accordance with design documentation

  • Inspect and verify conduit and pipe location and type in accordance with design documentation

  • Verify all items cast in are tied down or suitably restrained to prevent movement during concreting

  • Inspect and verify reinforcement size, location,, spacing, and lap lengths is within tolerances as per table B80.15, 16, 17

  • Reinforcement sufficiently secured with tying or tack welding (dependant on construction requirements)

  • Verify join to adjacent structure is prepared (roughened >3mm), ensure expansion joints are located, prepared, cleaned and in. The correct position

  • Submitted a certificate of compliance for formwork, reinforcement and embedments in accordance with hold point B80.7.3

  • HP released by:

  • Concrete temperature within tolerances (between 10 and 32degrees Celsius at point of discharge except for precast concrete members and cast in place piles where the temperature must be between 5 and 35 degrees)

  • Is the air temperature within tolerances. (Between 5 & 38 degrees Celsius in the shade or predicted to be below 5 degrees Celsius in the 24 hours after placement)

  • Measured volume of concrete pour

  • Concrete pour sheet reference number

  • Concrete test sheet reference number

  • Approval to pour

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.