Pre-Work

  • Adequate exclusion zones established with signage for public protection?<br>

  • All required training completed for work to be performed including site orientation?

  • MSDS Sheets obtained and available?

  • Pre Task Plan communicated, understood and signed by each crew member?

  • All required permits obtained?

Personal Protective Equipment

  • Dust masks

  • Welding hood

  • High visibility vests

  • Hearing protection

  • Safety glasses/side shields

  • Gloves

  • Work Boots

  • Hard hat bills foward

Fall Prevention

  • Material and debris secured from falling off parameter edge

  • Tools tethered off

  • Workers properly tied off

  • CAZ areas established with signs

  • Netting for exterior work in place

  • 100% Fall Protection for work above 6'

  • Floor opening protected and marked

  • Exclusion zones established below for exterior work

  • Parameter protection with max deflection of 3" maintained at 42" 21" with toe board and netting in place

Ladders and Scaffolding

  • Scaffold inspected and properly tagged

  • Components not damaged or modified and level

  • Sections properly pinned

  • Wheels locked on rolling scaffolds

  • Toe boards in place

  • Handrails in place

  • Extension ladders extend 36" above and secured

  • Platform ladders in use

  • Platform ladders in open position on level surface

Housekeeping

  • Materials stacked orderly and minimum of 10' from edge

  • Access/Egress to stairs, hoist, and through corridor maintained

  • Trash and debris removed from work area

  • Cords and hoses off floor

  • No trip hazards present

  • Area looks orderly

Hoisting and Rigging Equipment

  • Crane inspections complete

  • No overhead lifting

  • Lift signal used

  • Qualified rigger used

  • Rigging inspected and tagged

  • Tag line used

  • Swing radius barricaded

  • Safety latch on hook checked

  • Lift zone designated

Mobile Equipment and Aerial Lifts

  • Seatbelts used

  • Workers trained and certified

  • Equipment inspected

  • Backup alarms working

  • 10' separation from equipment

  • Exclusion zones established

  • Spotters used when needed

  • Workers tied off to anchor point

Excavations

  • Competent person named

  • Proper protective system

  • Excavation checked daily

  • Proper access/egress

  • Spoil pile 2' away from edge

  • Workers trained

Fencing and Barricades

  • Fencing closed, secured, and guarded

  • All sides of work area barricaded

  • Barricade properly placed and not creating hazard to public

Electrical

  • Electrical panels secured and LOTO systems used

  • All cords inspected and current color on cords

  • GFCI's used

  • Contractor Conducting Inspection

  • Inspected Contractor

  • Other

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.