  • Constraint 1.0 (Flood Barrier Shop Drawings) has been cleared

  • Constraint 6.0 (Incomplete Roofing at South Wall - CL e13, e17) has been cleared

  • Constraint 8.0 (Man Door Installation at South Wall - CL e9-e2) has been cleared

  • Constraint 13.0 (Gap in Wall at North Wall Level 4 - CL eE) has been cleared

  • Constraint 15.0 (Steel Pour stops & Metal Decking at South Soffit Skylights) has been cleared

  • Constraint 16.0 (Gas Meter Room Vents at South Wall - CL e15-e14) has been cleared

  • Constraint 17.0 (Pop Up Area Stud Framing at Level 3.5 - CL e5 & e8) has been cleared

  • Constraint 18.0 (Pop Up Area Roof Membrane Over Coping at CW along CL e5, eF,e8) has been cleared

  • Constraint 19.0 (Incomplete Roofing at Clearstory North Wall - Level 4 - CL eE) has been cleared

  • Constraint 21.0 (Coping Wood Blocking at South Clearstory - along CL eE) has been cleared

  • Constraint 25.0 (Missing Framing at CL e1-e2 Below Air Train Bridge) has been cleared

  • Constraint 26.0 (Masonry Walls Not Cleaned at East Wall CL eC-eD - Ground Level) has been cleared

  • Constraint 27.0 (Masonry Walls Not Cleaned at North Wall CL e1-e2 - Ground Level) has been cleared

  • Constraint 28.0 (Masonry Walls Not Cleared at Phase 1B East Wall - CL eF-eH Ground Level) has been cleared

  • Constraint 29.0 (East End Wall Above VCT at East) has been cleared

  • Constraint 31.0 (Roof Membrane @ Base of Wall at Generator Roof - East Wall) has been cleared

  • Constraint 32.0 (Roof Membrane @ Base of Wall at Generator Roof - North Wall) has been cleared

  • Constraint 33.0 (Interior Plenum Framing - East of EJ at Level 1.5) has been cleared

  • Constraint 34.0 (Missing Fire Caulk at level 1.5) has been cleared

  • Constraint 35.0 (Jersey Barriers and Shoring Materials in the way at South CL e17-e13) has been cleared

  • Constraint 36.0 (Spray Fireproofing not Completed at East between CL eB - eC along CL 3.2 @ Closure Wall) has been cleared

  • Constraint 37.0 (Roof Membrane @ Base of Wall at Clearstory Wall - CL e8 - e17) has been cleared

  • Constraint 38.0 (Parapet Framing at Gate T6-4) has been cleared

  • Constraint 39.0 (Parapet Roof Membrane at Gate T6-4) has been cleared

  • Constraint 40.0 (Parapet Framing at Stair tower at CL 15) has been cleared

  • Constraint 41.0 (Parapet Roof Membrane at Stair tower at CL 15) has been cleared

  • Constraint 42.0 (Parapet Framing at Lounge 3) has been cleared

  • Constraint 43.0 (Parapet Roof Membrane at Lounge 3) has been cleared

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.