JFK T6
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Constraints
-
Constraint 1.0 (Flood Barrier Shop Drawings) has been cleared
-
Constraint 6.0 (Incomplete Roofing at South Wall - CL e13, e17) has been cleared
-
Constraint 8.0 (Man Door Installation at South Wall - CL e9-e2) has been cleared
-
Constraint 13.0 (Gap in Wall at North Wall Level 4 - CL eE) has been cleared
-
Constraint 15.0 (Steel Pour stops & Metal Decking at South Soffit Skylights) has been cleared
-
Constraint 16.0 (Gas Meter Room Vents at South Wall - CL e15-e14) has been cleared
-
Constraint 17.0 (Pop Up Area Stud Framing at Level 3.5 - CL e5 & e8) has been cleared
-
Constraint 18.0 (Pop Up Area Roof Membrane Over Coping at CW along CL e5, eF,e8) has been cleared
-
Constraint 19.0 (Incomplete Roofing at Clearstory North Wall - Level 4 - CL eE) has been cleared
-
Constraint 21.0 (Coping Wood Blocking at South Clearstory - along CL eE) has been cleared
-
Constraint 25.0 (Missing Framing at CL e1-e2 Below Air Train Bridge) has been cleared
-
Constraint 26.0 (Masonry Walls Not Cleaned at East Wall CL eC-eD - Ground Level) has been cleared
-
Constraint 27.0 (Masonry Walls Not Cleaned at North Wall CL e1-e2 - Ground Level) has been cleared
-
Constraint 28.0 (Masonry Walls Not Cleared at Phase 1B East Wall - CL eF-eH Ground Level) has been cleared
-
Constraint 29.0 (East End Wall Above VCT at East) has been cleared
-
Constraint 31.0 (Roof Membrane @ Base of Wall at Generator Roof - East Wall) has been cleared
-
Constraint 32.0 (Roof Membrane @ Base of Wall at Generator Roof - North Wall) has been cleared
-
Constraint 33.0 (Interior Plenum Framing - East of EJ at Level 1.5) has been cleared
-
Constraint 34.0 (Missing Fire Caulk at level 1.5) has been cleared
-
Constraint 35.0 (Jersey Barriers and Shoring Materials in the way at South CL e17-e13) has been cleared
-
Constraint 36.0 (Spray Fireproofing not Completed at East between CL eB - eC along CL 3.2 @ Closure Wall) has been cleared
-
Constraint 37.0 (Roof Membrane @ Base of Wall at Clearstory Wall - CL e8 - e17) has been cleared
-
Constraint 38.0 (Parapet Framing at Gate T6-4) has been cleared
-
Constraint 39.0 (Parapet Roof Membrane at Gate T6-4) has been cleared
-
Constraint 40.0 (Parapet Framing at Stair tower at CL 15) has been cleared
-
Constraint 41.0 (Parapet Roof Membrane at Stair tower at CL 15) has been cleared
-
Constraint 42.0 (Parapet Framing at Lounge 3) has been cleared
-
Constraint 43.0 (Parapet Roof Membrane at Lounge 3) has been cleared