Information
-
Barclays
-
Conducted on:
-
Prepared by:
-
Location/Address
Pre-Visit Checks
-
Confirm "As Fixed" Drawings are available?
-
Have the property Lease demise plans been received from JLL?
-
If No, have the demise plans been requested/chased?
-
Is there a suitable R&D Asbestos Report available for this premise?
-
If No, has a new R&D Survey been requested?
-
Confirm date new report requested?
-
Please input planned Branch Closure date?
-
Please input the next Lease Break/Termination date (consultation with Estates Team may be required)
Building Status
-
Is the Building within a Conservation Area?
-
Is the Building Listed?
-
Are there any other "Local" status aligned to the Building?
-
What other status is aligned to the Building?
-
Could the Building be HRB (High Rise Building) applicable?
-
How many floors of Residential or Commercial Tenants reside above the Branch?
-
What is the approx dimension between the external pavement level & the floor level of the top storey? (Top storey does not include roof top Plant areas/rooms)
-
Approx how many Residential properties could there be above the Branch?
-
Are any areas of the building as a whole shared between the Branch & the Residents? (inc Plant areas)
-
Is the Branch within a Shopping Centre complex?
-
Confirm any restrictions associated to the Shopping Centre?
-
Will Shopping Centre Permits be required?
-
Insert Shopping Centre Contact details:
-
Does the premise have any Outbuildings/Garages or Extensions that are accessed independently?
-
If Yes, please indicate what type of Building it is, where it is & how its accessed?
-
Has access been gained to this particular Building?
-
Does this particular building contain any waste Materials (especially paperwork)?
-
What is required to gain access & are the branch team aware?
-
Does the premise have any Loft spaces?
-
Have all Loft spaces been accessed?
-
Has any waste materials (especially paperwork) been identified within this space?
-
Are any of the materials identified "Confidential"?
-
Have the branch team requested attendance to access this (these) areas?
External of Branch
-
Confirm Branch has a Letterbox? (if Yes, then capture photos Internally & Externally)
-
Branded Signage removal: Is Scaffolding, Scaffold Tower or Podiums required?<br>
-
What type of Access Equipment is required?
-
Will a Pavement Permit be required from the Local Authority to place the Access Equipment?
-
What is the dimension to the highest point of Signage/Projecting Sign?
-
Add media
-
Is Signage affixed to a Stone Facade or Fascia?
-
Will remedial works to the Stonework be required following the Signage removal?
-
Does the Branch have a Car Park facility?
-
Can the Car Park be secured?
-
How is the Car Park currently secured? If not currently secured, explain what needs to be provided upon completion of Closure works to secure it i.e. new chain/padlock or water barriers etc?
-
Explain why the Car Park cannot be secured?
-
Is there any Branded Signage that needs removing from the Car Park?
-
Is there any Branded Floor Markings that require "Burning Off"?
-
How many Parking spaces does the Branch have?
-
Add media
-
Is there any notable damage/vandalism to any External feature(i.e. Glazing) that should be addressed?
-
What is damaged/vandalised & where is it?
-
Please capture relevant Photos
External Self Service & Nightsafe
-
Is there any External Self Service machines? i.e. ATM, MDT etc
-
How many & what type are they?
-
Confirm facade make up that machines sit through? Glazing/Stonework/Marble/Render etc
-
Confirm approx aperture size of machine(s)
-
Confirm aperture infill works required? i.e. Infill existing aperture with matching stonework?
-
Will temporary propping be required to safely remove the Self Service machines?
-
If Yes, briefly outline your rationale?
-
Capture Photos Externally & Internally of each machine
-
Is there an existing Nightsafe?
-
Confirm facade make up that Nightsafe sits through? Glazing/Stonework/Marble/Render etc
-
Confirm approx aperture size of Nightsafe
-
Confirm aperture infill works required? i.e. Infill existing aperture with matching stonework?
-
Will the Nightsafe require any BWIC to remove it from its location? i.e. Breaking out concrete around it/Removing enclosure etc
-
If Yes, briefly outline the required works?
-
Will temporary propping be required to safely remove the Nightsafe?
-
If Yes, briefly outline your rationale?
-
Confirm approx dimensions of Nightsafe
-
Do the Branch Team have Keys for the Nightsafe?
-
Is the Nightsafe going to be removed?
-
Capture Photos Externally & Internally of Nightsafe
Access/Egress
-
Is there suitable parking for the Crate collection & Site Set Up delivery?
-
undefined
-
Add media
-
Confirm location of suitable Parking?
-
If No, what will be the suitable resolve?
-
Are there any Parking Restrictions to note, to assist with planning the Deliveries/Collections?
-
What will be the best form of Waste Removal - Placed Skips or Wait & Load vehicles?
-
If Placed Skip is preferred option, will any Permits be required?
-
Confirm location of Placed Skip?
-
Photos required of both proposed Parking & Placed Skip locations
Entrance, Banking Hall & FOH
-
What Type of Outer Door(s) does the Branch have?
-
Confirm dimensions of clear open width of Outer Door(s)?
-
Does Branch have an Internal Door(s)?
-
What Type of Inner Door(s) does the Branch have?
-
Confirm dimensions of clear open width of Inner Door(s)?
-
Does the Branch have a Secondary Entrance?
-
Photos required Internally/Externally of Outer & Inner Doors
-
What type of Counterline is present?
-
Photos required from both sides of Counterline
-
Please capture photos of Counter Cash Drawer Units
-
Please confirm height of Banking Hall ceiling?
-
Do Roller (or alternative) Blinds obscure the full view into the Branch?
-
If No, will Corex(or similar) be required?
-
Is the Branch in a prominent area & as such require Frosted Window Filming instead?
-
Photos required from within the Banking Hall of the external windows
-
What appears to be the Make Up of the Banking Hall Floor? Concrete or Timber?
-
Is the Floor Raised?
-
Is there a Passenger Lift present?
-
Is the Lift in Use/Operational?
-
Confirm Model details inc Loading Capacity & clear opening width of Car doors?
-
Photos required
-
Is there any Escalators present?
-
Are the Escalators in Use/Operational?
-
Photos required
-
Are there any Internal ATM's?
-
Photos required from both sides - inc Model Plate
-
Are there any QSP's?
-
Photos required from both sides - inc Model Plate
-
Are there any Kiosks / OLBP's?
-
Photos required
-
Are there any ASC's/ASD's?
-
Photos required from both side - inc Model Plate
-
Is there a QPP?
-
Photos required from both sides
-
Is there any other notable Self Service machines in the Branch?
-
Provide details of other SS machines?
-
Provide Photos of other SS machines
-
Will temporary propping be required to remove any of the Self Service machines?
-
If Yes, please briefly explain your rationale?
-
Are there any "Current Deployment" elements that should be retained? Furniture or Technology?
-
Please detail identified elements?
Cash Office, Secure Area & BOH Areas
-
Does the branch have a TRAKA Key Box?
-
Does the branch have a Bio-Metric Airlock?
-
If Yes, please capture photos of the associated PC aswell
-
Does the branch have an I-Safe?
-
Is there a Bullion Hoist?
-
Is there a Dumb Waiter/Ad Hoc Hoist?
-
Confirm how many Cash Trollies are being removed?
-
Please confirm the ceiling height within the Cash Office area?
-
Do any Windows within the Ground Floor BoH area need obscuring?
-
If Yes, please detail what windows?
Cash Safes & Strong Rooms
-
Are there any Double Cash Safe(s)?
-
How many Double Cash Safes are there?
-
Please capture the O/A dimensions of the Safe(s)?
-
Will the Cash Safe(s) be removed?
-
What concerns if any will there be when removing the Safe(s)?
-
Provide Photos of the Safe(s) including the KABA Locks
-
Do the Branch Team have Keys?
-
Are there any Single Cash Safe(s)?
-
How many Single Cash Safes are there?
-
Please capture the O/A dimensions of the Safe(s)?
-
Will the Cash Safe(s) be removed?
-
What concerns if any will there be when removing the Safe(s)?
-
Provide Photos of the Safe(s) including KABA Locks
-
Do the Branch Team have Keys?
-
Are there any other notable Cash Safes within the Branch? i.e. Transfer Safe etc
-
Please detail the additional Cash Safe(s)?
-
Provide Photos of additional Cash Safe(s)
-
Is there a Strong Room?
-
Provide Photos including Outer Door & KABA Locks
-
Do the Branch Team have Keys?
-
Is there a Book Room?
-
Provide Photos including Outer Door & KABA Locks
-
Do the Branch Team have Keys?
-
Does the Branch have a Pre-Fabricated Strong Room?
-
Will the Pre-Fab Strong Room be removed?
-
Provide Photos including the Outer Door & KABA Locks
-
Will any of the Cash holding elements, require removal from Lower/Upper Floors?
-
If Yes, what floor will this be from? i.e. Basement, First Floor etc
-
Will Crane Lifts or Specialist Access equipment be required?
-
Please detail the likely involvement for these works? i.e. Crane lift, with window removal etc
Security Systems
-
Is there a Perimeter Intruder Alarm system in use at Branch?
-
If Yes, please capture Photos of Main Panel & IRIS Unit inc other notable elements
-
Does the Branch have a Standard CCTV system in place?
-
Please confirm how many "Ways" it has? i.e. 8 or 16
-
Does the Branch have a Sole Control CCTV system in place?
-
Please confirm how many "Ways" it has? i.e. 8 or 16
-
Please provide Photos of the CCTV Intellex Units within their Cabinets
-
Does the Branch have a "Smoke & Dye" system in place?
-
Does the Branch have a "Smoke Cloak" system in place?
-
Are there any other Security systems in place that we should be aware of?
-
Please record any notable elements?
MEP
-
Is there Air Conditioning within the building? (Please ensure both Internal & External locations are captured on MS Drawings)
-
Please record the quantity of Internal Units i.e. Wall Mounted, Ceiling Cassette or Linear Grilles
-
Please record the quantity of External Condensers i.e. Splits or VRV's/VRF's
-
Please capture Photos of both Internal & External AC elements
-
Is there safe means of Access to the External AC Plant?
-
Please identify the current means of Access to the External AC Plant?
-
Please advise as to what is required to safely Access the External AC Plant area?
-
Please capture Photos of existing AC Plant area & routes leading to it
-
Is there a Fire Alarm system within the Branch? (Please ensure the Fire Alarm panel location is captured on the MS Drawings)
-
Is the Fire Alarm system shared with a 3rd Party?
-
Who is FA shared with? (i.e. Residents or Commercial Tenants above/adjoining)
-
Is there an existing Fire Alarm Zonal Chart in place?
-
Will a new FA Zonal Chart be required?
-
Please ensure Photos are captured of the Fire Alarm Panel & Zonal Chart
-
Is there a Gas Meter within the Branch? (Please ensure the Gas Meter location is captured on the MS drawings)
-
Is the Gas supply shared with a 3rd Party?
-
Please ensure Photos are captured of the Gas Meter
-
Can the Water Meter be located? (Please ensure that the Water Meter location is captured on the MS Drawings)
-
Is the Water supply shared with a 3rd Party?
-
Please ensure Photos are captured of the Water Meter
-
Can the Electric Meter be located? (Please ensure that the Electric Meter location is captured on the MS Drawings)
-
Is the Electrical supply shared with a 3rd Party?
-
Please ensure Photos are captured of the Electric Meter
-
Please ensure Photos are captured of all Distribution Boards & Label Charts
-
Is there any existing Boilers within the Branch? (Please ensure that any Boiler locations are captured on the MS Drawings)
-
Are Boiler(s) shared with a 3rd Party?
-
Please ensure Photos are captured of all Boilers
-
Does the Branch have Radon?
-
Please ensure that the Radon system location is captured on the MS Drawings
-
Please ensure Photos of the Radon system are captured
-
Does the premise have any Sump Pumps?
-
Is the Sump Pump(s) working?
-
Will any MEP elements require removing/relocating to facilitate the Closure works?
-
Please highlight within the MS Drawings elements for removal/relocation i.e. AC Units, Power, Controls, FA Call Points etc
-
Provide Photos of MEP elements that require removing/relocating
-
Are there any notable elements of M&E that appear to be not working? (i.e. Lighting, AC etc)
-
Please detail the issue noted & provide photos?
Notes:
-
Size of Branch
-
Expected Program Duration(Standard is 2 weeks)
-
Are there Residential or Commercial properties above the Branch?
-
Please advise on any concerns this may bring?
-
Any other issues or elements to note?
-
Are there any "bespoke" elements installed within the Branch that may not be obvious without asking a Branch Colleague?
-
Please detail what "bespoke" item is within the Branch
-
Any other relative photos required?