Step -1-
-
Carefully read all notes on the Doka drawing.
-
Inspect all fall protection.
-
Remove ties and disconnect formwork cornes.
-
Pull all nails from openings.
-
Disconnect newly cast anchor from formwork.
-
Cut all the bolts from the embeds.
-
Release traveling unit locking wedges.
Step -2-
-
Retract the traveling unit with formwork attached and lock wedge.
-
Prepare the next suspension point (Cone Bolt B7)
-
Remove wood from openings.
-
Clean off platforms.
-
Detach the wind straps.
Step -3-
-
Move traveling unit close to center of gravity.
-
-
Prep safety hand rail to jump.
-
Place the correct signage ( fall protection, red tape, scaffold tag, ext.) .
-
Ground man is in place and ready to spot.
-
Attach crane to vertical profile lifting points.
-
Undo the safety pins from horizontal profile.
-
All workers vacate platform.
-
Hoist the formwork until with the crane and hook into prepared suspension points.
-
Replace the safety pins in horizontal profile.
-
Secure all handrails and safety net.
Step - 4 -
-
Attach the wind straps.
Step - 5-
-
Verify Doka material is installed per Doka Drawings and user Information.
-
Baker Concrete. Competent Person Signature.