Title Page
-
Building
-
Area
-
Elevation
-
Works
-
Certa Manager
Installation
Installation Works
-
Type of works
-
Have correct materials been delivered to site?
-
Install Galv perimeter upstand
-
Primer onto Concrete slab
-
Install Torch on VCL
-
Install PU Adhesive
-
Install Enetherm PIR Insulation Board
-
Prime Insulation with Bonding agent
-
Install heat activated (torch on) underlay
-
Install torch on Cap sheet
-
Evidence
-
Has Correct material been delivered to site?
-
Install VCL layer onto Roofdeck
-
Install IKO PIR insulation
-
Install Armourplan P SPM
-
Install IKOFIX Peelstop bar fixed with perimeter fixing at 250mm centres
-
Install IKO Membrane cover strap
-
Electronic integrity test carried out
-
Evidence
-
Has correct Material been delivered to site
-
Install Novia FR Breather Membrane across face of SFS & sheathing boards.
-
Install 220mm deep Euroclad Quattro spacer system
-
Install 220mm Knauf Factoryclad 40 insulation
-
Install 0.7mm steel Prisma coated (RA7012) 32/1000R profile with class A Butyl mastic seals and stainless steel fixings
-
Install External flashings with class A Butyl mastic seals and stainless steel fixings
-
Clean down area
Snagging
Snagging
-
Have any Snags been identified?
-
Photo
-
Have Snags been Rectified?
-
Photo
Senior Manager QA Checks and Handover
Certa QA Manager Final (or Senior Certa Manager) Inspection
-
Have all items on QA form been filled in?
-
Have any 3rd party test or inspection reports been carried out?
-
Is area snag free and ready for handover?
-
Have final QA checks been carried out?
-
Is area ready for handover?
Handover
-
On behalf of Certa Roofing and Cladding LTD
-
Signature
-
On behalf of KIER
-
Signature