Title Page

  • Project:

  • Building

  • Area

  • Type of works

  • Commencement date

  • Main contractor:

  • Certa Manager

Pre work checklist

  • Design Approved

  • Materials Approved

  • Personnel Competent

  • Risk Assessments & Method Statements Developed

  • Temporary Works Approved

  • Preceding Works Handed Over

Areas of work

Specific inspections

  • Type of works

  • Roofing Type

  • Roof system

  • Acceptance of Sub-Structure

  • Construction of various benchmarks

  • Materials checked before use

  • Client Set Out Gridlines & Datum

  • Install Outlets

  • Primary layer IKO Permatec Compound (3mm thickness)

  • IKO Permaflash-R reinforcement layer

  • Secondary layer IKO Permatec Compound (3mm thickness)

  • Capsheet: IKO Permagurad-F

  • Electronic leak test

  • IKO Enertherm XPS insulation (tightly abutted)

  • IKO Enertherm WCL (water control layer)

  • 50mm thick pre-cast concrete pavers on 15mm supports or washed rounded ballast

  • Acceptance of Sub-Structure

  • Construction of various benchmarks

  • Materials checked before use

  • Client Set Out Gridlines & Datum

  • Apply Bonding agent to existing SR35 metal deck

  • Apply self adhesive VCL – note bonding agent and VCL will be installed in unison

  • Install tapered Enetherm insulation system (ensure tight abutment)

  • Mechanically fixed IKO Armourplan P

  • Gutters installed with overflows

  • Interfaces and details

  • Electronic integrity test

  • Acceptance of Sub-Structure

  • Construction of various benchmarks

  • Materials checked before use

  • Client Set Out Gridlines & Datum

  • Install SR35 decking system with SWRP50 sealant tape at all side laps

  • Fixings at end laps- 7no. JT3-3-5.5x50 S16

  • Fixings at intermediate - 4no. JT3-3-5.5x50 S16

  • Fixings at side laps - 450 ctrs JT2-3-5.5x25 S16

  • Mesa Aluminium Support Joists (40mm x 50mm) 3600mm Long - 600mm max centres

  • 50mm x 35mm Galv Joist Brackets Installed at 600mm MAXIMUM centres

  • Envirobuild 145 Pro-Grip Aluminium Decking Board 3600mm Long x 145mm wide + 5mm joint gap 150mm module width Fixed with secret fix "T" brackets, fixed into joists at 600mm max centres

  • Type of cladding

  • Acceptance of Sub-Structure

  • Construction of various benchmarks

  • Materials checked before use

  • Client Set Out Gridlines & Datum

  • Remover currently installed siniat board

  • Install Siniat board horizontally in a staggered pattern fixed into SFS frame

  • For fixing boards to SFS up to 3mm Thick: TBF-4.8x30

  • For fixing boards to Steel Members from to 4mm-10mm Thick: WDHS-5.5x65

  • Apply sealant as boarding progresses, along the previously fixed board edge prior to installation of the next board. Apply sufficient sealant to create a sealant joint of approx 2mm when the next board is loosely butted

  • Acceptance of Sub-Structure

  • Construction of various benchmarks

  • Materials checked before use

  • Client Set Out Gridlines & Datum

  • Establish movement joints

  • Single / Double Helping-Hands w/Thermal Iso Pad fixed back to SFS Framing. Vertical Max cts = 800mm. Horizontal Max cts = 600mm

  • Vertical 'Tee' Rail (RS-F) fixed to Helping-Hands. RS-F Max Extension beyond Helping hand is 300mm. Min 'Tee' to 'Tee' Joint Spacing = 8mm

  • PVC Isolation Tape applied to from face of 'Tee' Rail

  • Magnelis Steel Brick Cassette, 2.4m Standard fixed to Vertical 'T' Rail. Cassette to be staggered from the one above - 1.2m from end. Min Cassette to Cassette Spacing 2mm

  • Brick fixed into Cassette (10mm Joints). 65mm x 25mm x 215mm (Full) or 102.5mm (Half)

  • 2 piece vents installed

  • Once all Bricks are installed, inject Mortar to all joints. Complete & continuous filling, slightly overfilled at the front. Pointing tool used to compress & create desired finish.

  • Acceptance of Sub-Structure

  • Construction of various benchmarks

  • Materials checked before use

  • Client Set Out Gridlines & Datum

  • Breather membrane installed with barrier tape

  • Single / Double Helping-Hands w/Thermal Iso Pad (Nvelope NV1 Series) fixed back to SFS Framing. Vertical Max cts = 800mm. Horizontal Max cts = 600mm.

  • Vertical ‘T’ Rail & Vertical ‘L’ Rail fixed to Helping-Hands

  • Swisspearl Carat Fibre Cement Board fixed into ‘T’ & ‘L’ rails using Swisspearl Aluminium Rivets RIV-A EPDM 4.0x20mm

  • Install Multifix brackets fixed to SFS w/2.No JT3-3-5.5x50-S16 (150mm max from both ends & 500mm max centers)

  • Vertical closed state barriers are continuous with open-state horizontal barriers abutting

  • Fire barriers mitred at external corners, seal joints with AIM Sealant.

  • Vertical fire barrier compression to be min 5mm

  • Fire barriers tightly abutted

  • Bags to be re taped if cut

Handovers

  • Has area been snagged?

  • Have all snags been closed out?

  • Is area ready for handover?

  • Final QA Photos

  • Certa Manager signature

  • Main contractor signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.