Title Page

  • Building

  • Area

  • Elevation

  • Works

  • Commencement date

  • Certa Manager

Work installation and inspection

Pre-install checklist

  • Does site have construction issue drawings available?

  • Have project specific calculations & drawings been developed for the system?

  • Is the substructure in line with current system tolerances?

  • Have grid lines and Datum’s provided by HBC?

  • Have any changes in design been approved?

  • Is area clear and accessible?

Installation

  • Type of works

SFS

  • Has SFS been set out to gridline/Datum?

  • Has SFS been installed correctly?

  • Has SFS been checked by Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

Boards

  • Has correct material been delivered to site?

  • Have liner boards been installed in line with Certa construction issue specs?

  • Have liner boards been checked by a Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

Breather membrane

  • Has correct material been delivered to site.

  • Has breather membrane been installed inline with Certa construction issue specs?

  • Has breather membrane been checked by a Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

Brackets

  • Has correct material been delivered to site?

  • Have correct fixings been identified?

  • Have brackets been installed in line with certa construction issue specs?

  • Have brackets been checked by Certa manager

  • Can next stage of installation be carried out?

  • Evidence

Fire barrier

  • Has fire barrier been installed to the latest fire strategy revision?

  • Has fire barrier been installed in line with Certa construction issue specs?

  • Has fire barrier been checked by Certa Manager

  • Can next stage of installation be carried out?

  • Evidence

  • Hold Point Sign off

Duoslab insulation

  • Have correct material been delivered to site?

  • Has Insulation been installed with correct fixings in line with Certa Construction issue specs?

  • Has Insulation been checked by Certa Manager

  • Can next stage of install be carried out?

  • Evidence

Corten panels

  • Has correct material been delivered to site?

  • Have Corten panels been installed in line with Certa construction issue specs?

  • Have Corten panels been checked by Certa Manager?

  • Is area ready for final QA inspection?

  • Evidence

Decking roof & Top Hats

  • Decking installed in line with Certa construction issue specs?

  • Top hats installed in line with Certa construction issue specs?

  • Brackets installed to correct centres?

  • Works checked by Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

VCL

  • VCL installed in line with Certa Construction issue specs?

  • VCL checked by Certa Manager

  • Can next stage of installation be carried out?

  • Evidence

Duoslab insulation

  • Insulation installed in line with Certa Construction issue specs?

  • Works checked by Certa Manager

  • Can next stage of installation be carried out?

  • Evidence

Bemo panels

  • Bemo panels installed in line with Certa construction issue specs?

  • Works checked by Certa Manager

  • Can next stage of installation be carried out?

  • Evidence

Corten panels

  • Corten panels installed in line with Certa construction issue specs?

  • Works checked by Certa Manager

  • Area ready for final QA checks

  • Evidence

Priming

  • Sopradvance fast curing compound installed?

  • Elastico 500 primer installed?

  • Duoflex compound 1st layer installed?

  • TR200 reinforcement fleece installed?

  • Duoflex compound 2nd layer installed?

  • Sopralene Flam Garden 250 AF cap sheet installed?

  • Priming installation checked by Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

Insulation

  • 180mm Sopratherm XPS SL artic insulation installed?

  • Ecovoid and filter layer installed?

  • Insulation checked by Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

Paving

  • Paving installed

  • Paving checked by Certa Manager

  • Area ready for final QA checks?

  • Evidence

Decking

  • Has correct material delivered to site?

  • Have decking sheets been installed to Certa construction issue specs?

  • Has decking been checked by a Certa Manager?

  • Can next stage of installation be installed

  • Evidence

VCL

  • Has correct material been delivered to site?

  • Has VCL been installed to Certa Construction issue drawings?

  • Has VCL been checked by a Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

Insulation

  • Has correct material been delivered to site?

  • Has insulation been installed in line with Certa Construction issue specs?

  • Has insulation been checked by Certa Manager?

  • Can next stage of installation be carried out?

  • Evidence

Single ply

  • Has correct material been delivered to site?

  • Has single ply been installed in line with Certa Construction issue specs and Soprema installation guidelines?

  • Has single ply been checked by Certa Manager?

  • is area ready for final QA inspection?

  • Evidence

undefined

  • Has correct material been delivered to site?

  • Have tiles been installed in line with Certa Construction issue specs?

  • Have tiles been checked by Certa Manager?

  • Is area ready for final QA checks?

  • Evidence

SFS

  • Have correct materials been delivered to site?

  • Has SFS been installed in line with Certa construction issue specs?

  • Has SFS been checked by a Certa Manager?

  • Can next stage of installation be carried out?

Board

  • Has correct material been delivered to site?

  • Has Board been installed in line with Certa Construction issue specs?

  • Have Boards been checked by a Certa Manager?

  • Can next stage of installation be carried out?

Membrane

  • Has correct material been delivered to site?

  • Has Membrane been installed inline with <br>Certa construction issue specs?

  • Has Membrane been checked by a Certa Manager?

  • Can next stage of Installation be carried out?

Rails and Hooks

  • Has correct material been delivered to site?

  • Have rails and hooks been installed in line with Certa Construction issue specs?

  • Have rail and hooks been checked by a Certa Manager?

  • Can next stage of installtion be carried out?

Fire Barrier

  • Has fire barrier been installed to the latest fire strategy revision?

  • Has Fire barrier been checked by a Certa manager?

  • Can next stage of Installation be carried out?

Cladding and fins

  • Has correct Material been delivered to site?

  • Has Cladding and Fins been installed in line with Certa construction issue specs?

  • Have cladding and fins been checked by a Certa manager?

  • Is area ready for snagging?

  • Evidence

Snags

  • Have any snags been identified

  • Photo any snags found

  • Photo snags closed out

  • Is area ready for final QA inspection

Final inspection and handover

Final QA check (to be carried out by Certa QA Manager other Senior Certa Manager)

  • Has all relevant QA checks been carried out on this document and sufficiently answered?

  • Has evidence been provided for relevant sections?

  • Has area been checked for a final quality?

  • Is area ready for handover?

  • Final QA photos

Sign off

  • Certa QA manager or Senior Manager

  • Client representative

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.