  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • What are the details of the installation? (Gas, Vessel size, Serial number)

  • Has separation and segregation of the Cryospeed vessel been achieved in accordance with AS1894-1997 table 1.5 (or table 4.1 for liquid oxygen?)

  • Is there adequate access for tanker delivery?

  • Does the installation follow standard drawing number E405-1938_S1 Standard CRYOSPEED Cryotank Installation?

  • Has the safety station been securely mounted to either a suitably load bearing wall or safety station stand?

  • Is the safety station installed a minimum of 2 metres away from the Cryotank?

  • Is the Cryotank located on a flat stable surface?

  • Is the installation on a secure site?

  • If the site is not secure, has an adequate security fence been installed?

  • Is there adequate vehicle protection in place?

  • Has the Cryotank been bolted down?

  • Have the gas discharge ports been installed so as not to introduce a hazardous area?

  • Have the following signs/placards been erected?

  • Has all commissioning and handover documentation been completed?

  • Has the customer handover procedure been followed and recorded?

  • Has fixed installation pricing been used as detailed in SRM?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.