Information
-
Document number
-
Facade Name
-
Elevation
-
Level
-
Conducted on
-
Prepared by- LIDER
Inspection
-
Is the correct bracket used?
-
If anchor bolt: Is the correct size and length used?
-
If anchor bolt: Is the correct thread depth achieved past the marker?
-
If halfen channel: Is the T-bolt fully engaged in the halfen channel?
-
If halfen channel: Is the T-bolt engagement indicator in the right position?
-
Are the correct fixings used? i.e. nuts; washers
-
Minimum of three threads above nut achieved?
-
Are the brackets setup as per drawings provided by AYGÜN?
-
Correct torque achieved?
-
Brackets sprayed with blue paint?
Additional comments
-
undefined
Handover
-
Tested by
-
Witnessed by
-
Mace