Information
-
Project Name
-
Date Completed
-
Completed by
-
Location
-
Project Team Foreman, Superintendent, PM, Designer
Design
Design
-
Was field engaged for the design?<br>Superintendent, Foreman etc.
-
Was there a design turnover meeting?
-
Have we coordinated with other trades?
-
Is there an approved set of all trades coordination drawing?
-
Was there a design review?
-
Is the design complete and on time?
-
Are there critical details shown on plans?
-
Are pipes labeled / dimensions / elevations / typical pieces / etc.?
Fabrication
-
Does vendor have contract / PO with terms and conditions?
-
Is fabricator aware of our specifications and quality expectations?
-
Does the fabrication meet our quality expectations?
-
Is the fabrication on time?
-
Do we have a fabrication schedule?
-
Is pipe bundled by line color?
-
Is pre-fabrication being utilized?<br>Hangers, stands, etc.
Scheduling / Mobilization / Delivery
-
Do we have a schedule?
-
Does the current schedule match the bid documents schedule?
-
Can we meet the schedule?
-
Are we on schedule?
-
Do we have the required man-power available?
-
Was there a turnover meeting with field?
-
Did the foreman get a field packet?
-
Does foreman have all contact names and phone numbers?
-
Does the foreman understand the scope of work?
-
Have deliveries been schedule with GC?
-
Is there a plan for accepting deliveries?
-
Do we have a lay-down area?
-
Can we remain in this lay-down area for the duration of the projects?
-
Do we have carts / forklifts / cartage to accept material?
Installation
-
Is there a complete set of prints for the entire job?
-
Did a Daily Huddle occur before work began today?
-
Was the Daily Huddle documented?
-
Are carts, bins or racks being utilized?
-
Are the correct lifts being utilized?
-
Are the foreman and crew qualified?
-
Has the crew been trained in proper use of their tools?
-
Has the crew received the required safety training as it relates to the project? <br>Lift, OSHA, Confined Space, etc.
-
Are we following QC protocols and company policies?
-
Is the project being installed per the plans?
-
Are we running the project or is it running us?
-
Is the crew utilizing technology?
Project Management
-
Is Project Manager involved?
-
Has Project Manager completed regular KISS site safety audits?
-
Do we have the appropriate labor mix?
-
Does field have a phase sheet?
-
Does foreman know what the budgeted hours per head is?
-
Have the hours per head been compared to historical data?
-
Is crew setting daily and weekly production goals?
-
Do they meet or exceed the budget?
-
Are we performing monthly "Cost to Complete"?
-
Is foreman and PM tracking changes?
-
Are we current with all change order pricing?
-
Are we attending job meetings? Who attends?
Accountability
-
Is the crew and project safe?
-
Is WSFP and other trades housekeeping acceptable?
-
Is there a quality control plan?
-
Have we set expectations?
-
Are we inspecting what we expect?
-
Are we holding vendors and other trades accountable?
-
Are we pursuing back charges?
-
Does everyone on the project understand the WSFP Loss Prevention Policies and our Health & Safety Program?
Sister Branch Program
-
Is the sister branch program being utilized?
-
Has the program been illustrated to the branch superintendent?
-
Is the superintendent utilizing the minimum standards?<br>QAMM
-
How many qualify for the Incentive Program?