Information
-
Job Name
-
Job Number
-
Report Date (YYYYMMDD)
-
Superintendent
-
Project Manager
-
Location
Specifics
-
Placement date:
-
Location:
-
Pour Number:
-
Pour type:
- Paving
- C&G
- Sidewalk
- Exterior Steps
- Site Footings
- Site Walls
- Light Pole Bases
- Drilled Piers
- Pier Caps
- Spread Footings
- Gradebeams
- Slab on Grade
- Pits
- Trenches
- Building Walls
- Columns
- Elevated Deck
- Slab on Metal Deck
- Topping Slab
- Stairs and Landings
- Metal Pan Stairs
- Tilt Up Panel
- Other
-
Pour Type:
-
Projected Ambient Temperature:
-
Pour Method:
-
Pour Method:
-
Pour Rate:
-
Mix Design:
-
Slump (list minimum and maximum)
-
Air % (list minimum and maximum)
-
Pour Specific Admixtures:
-
Estimated Concrete Quantity (CY):
-
Formwork (SF):
-
Finished Surface (SF):
-
Linear Feet Forms (FT):
-
# Embeds:
-
# Anchor Bolts:
Pre pour
SUBGRADE
-
Subgrade Elevation
-
Bearing Capacity
-
Clean Footing
-
Final Grade Elevation
-
Vapor Barrier
FORMWORK
-
Line & Grade
-
Grade Nails
-
Chamfer
-
Keyway
-
Waterstop
-
Oiled
-
Blockouts
-
Expansion Joints
-
Mason/Dovetail
-
Forms
EMBEDS
-
Anchor Bolts
-
Pipe Sleeves
-
Misc. Metal
-
Lentons/Formsavers
-
Rebar
-
Post Tensioning
Scheduling/Delivery
CONCRETE PLACEMENT
-
Personnel
-
Truck/Pump/Crane
EQUIPMENT
-
Vibrators
-
Buckets
-
Termites
FINISH EQUIPMENT
-
Hand Tools
-
Screed
-
Cure
-
Saw
PERSONNEL
-
Pour Watch
-
Placing
-
Finishers
CONTINGENCY PLANNING
-
Equipment
-
Delivery
-
Weather
TESTING/INSPECTION
-
Testing Lab Scheduled
-
City/County Inspection
Signatures
STRUCTURAL
-
Rebar Installer
-
Project Engineer
-
Field Superintendent
-
Structural Engineer
-
Independent Inspection
-
Post Tensioning
-
SUBCONTRACTORS
-
Mechanical
-
Electrical
-
Fire Protection
-
Plumbing
-
Formwork
OTHER
-
MEP Coordinator
-
General Contractor
-
QC Review
Post Pour
POST POUR REPORT
-
Actual Start Time
-
Actual Finish Time
-
Total Yards
-
Pour Rate (CY/HR)
-
Comments
Photos
-
Photos