General Info
-
CCF Crew Leader Name:
-
Crew Leader Phone #:
-
GC/Client Superintendent Name:
-
Super. Phone #/Email:
-
GC/Client PM Name:
-
PM Phone/Email:
-
Notes:
Safety
-
Safety Meeting Requirements
-
PPE Requirements
-
Job specific hazards
-
Safety reporting requirements
-
Safety Notes:
Job Conditions/Logistics
-
Is there climate control in the building?
-
Is there adequate lighting?
-
Are floor drains level and plumb with an adjustable cover set within the desired finish floor elevation as determined by the plans/design intent?
-
Is the floor free from Sheetrock mud and broom swept?
-
Is Sheetrock within 1/2" of floor?
-
Moisture Testing Results
- acceptable
- not acceptable
- not done
- inconclusive
-
Location for stored materials:
-
Is there a forklift available for moving material?
-
Job Conditions/Logistics Notes:
Quality
Ceramic
-
Is there ceramic scope of work?
-
Grout joint sizes selected?
-
Grout Joint Sizes:
-
Are marble thresholds required?
-
Is epoxy thinset required?
-
Is epoxy grout required?
-
Is waterproofing required?
-
Where is waterproofing required?
-
Is crack isolation required?
-
Where is crack isolation required?
-
Is a mudbed required?
-
Is wire mesh required?
-
Is a slip sheet required?
-
Location for sand and cement:
-
Mock-Up Requirements:
-
Are elevations clear for wall tile?
-
Were the specs reviewed with GC/client?
-
Ceramic Notes:
Resilient Tile/Plank
-
Is there a vinyl tile/plank scope of work?
-
Installation direction of tiles:
-
Were the specs reviewed with GC/client?
Carpet
-
Is there a carpet scope of work?
-
Is there broadloom in the scope of work?
-
Is there pattern carpet?
-
Do seam locations need to be reviewed with the architect?
-
Is there carpet tile in the scope of work?
-
Direction of carpet tile?
- straightlay/monolithic
- ashlar
- random
- quarter turn
- other
- need selection
Resilient Sheet Goods
-
Is there sheet products scope of work?
-
Review seam locations:
-
Is flash cove required?
-
Height of flash cove:
-
Type/finish of cove cap:
-
Resilient Sheet Goods Notes:
Resilient Base and Accessories
-
Is there a rubber base/molding scope of work?
-
Is wall covering specified at rubber base locations?
-
Wall covering should be held up off of the floor to 1/2" below top of base.
-
Are pre-molded base corners spec'd?
-
Has an RFI been sent to request job built corners? If no, will GC sent request?
-
Is the base Tight-Lock?
-
Is there a rubber chair rail scope of work?
-
Walls should not be painted where chair rail is spec'd.
-
Resilient Base and Accessories Notes:
Schedule
-
Is the project currently on schedule (other trades)?
-
Proposed start date:
-
Proposed duration:
-
Working hours:
-
Upon notification of installation readiness, what does the GC anticipate the condition of the area to be installed (finished status, lighting, ceilings, other trades, etc.)?
-
Is the area to be floored free from interference by other trades?
-
Is flooring being scheduled out of sequence?
-
NOTE TO GC: Flooring is being scheduled out of sequence based on industry standards. Cornerstone will not be held responsible for cost to perform repairs or material shortages due to damages by others.
-
Schedule Notes:
Contract/Cost
-
Has contract been reviewed with GC?
-
Change Order and Extra Work Procedure:
-
Cornerstone will require a formal change order for extra work and/or repair work prior to proceeding, except for floor patch.
-
Floor patch procedure: Cornerstone will present empty units of floor patch to superintendent for verification of quantities. Cornerstone will present superintendent with a patch sheet for signature. Cornerstone will issue a COR to project manager for issuance of a formal change order.
-
Has the floor patch procedure been reviewed with client and do they agree with policy?
-
Contract Notes:
Other
-
Insert Jobsite Pictures
-
Notes:
-