Title Page

  • Community

  • Lot Number(s)

  • Conducted on

  • Prepared by

Foundation Checklist Pre-Pour

  • Form dimensions match plans

  • Penetrometer test completed. Attach scan of results to this form prior to submitting.

  • Plumbing verticals are in correct locations and fall within walls.

  • Main water sleeve in place, located within 2-3 feet of intended water shut off location

  • Plumbing located within footings are protected by sleeves

  • Plumbing verticals are decoupled from slab

  • Plumbing in footings has rebar saddle

  • Island conduit is in place, ends are capped. Conduit to be placed minimum 2-3” under vapor barrier and backfilled

  • Confirm if selections have any floor outlets @ 1st floor

  • Ufer Rod is in place and located within 2-3 feet of intended meter location

  • Verify top of slab for houses in flood zones. List measurements in notes section. Under construction Flood Cert scheduled

  • Benchmark Elevation

  • Slab height above BM

  • Benchmark Elevation

  • Slab height above BM

  • Foundation hold down locations spray painted on form boards

  • T-pole is in place and meter installed

  • Dumpsters in place

  • Lot signage in place including permit box

  • Port-a-let on site or maximum 3 lots away

Required Documents

  • Penetrometer test results

Signature

  • Superintendent Signature

  • Date completed

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.