Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Mechanical Contractor
-
Is duct installed?
-
Is duct testing complete and inspected by City/Owner/CA?
-
Are flex connectors installed on duct connections?
-
Are dampers installed and operation verified?
-
If dampers are not automatic all dampers shall be manually opened for start up purposes only.
-
Is the unit cleaned and filters installed?
-
Are all shipping bolts removed?
-
Have the motors and belts been checked for tension and alignment?
-
Is heating water piping installed per contract documents?
-
Is chilled water piping installed per contract documents?
-
Have all fins been combed/straightened on the coils?
-
Is access for service provided?
-
Are condensate traps piped and vented with proper trap seal and grade?
-
Is piping and equipment labeling complete?
-
Are all GRDs installed?
-
Add signature
Electrical Contractor
-
Is power available to disconnect/starter/vfd?
-
Is access to electrical clear and installed per NEC?
-
Are all interior lights and service outlets verified on?
-
Add signature
Control Contractor
-
Is access to control devices provided?
-
Has control contractor completed wiring to devices?
-
All safeties must be enabled. (Freeze stats, high duct static, etc.)
-
Is unit ready for point to point check out?
-
Add signature
Insulation Contractor
-
Is insulation completed on duct and piping per specifications?
-
Add signature
Fire Alarm Contractor
-
Are smoke detectors installed and wired?
-
Add signature
General Contractor
-
Is area served cleaned and dust free?
-
Add signature
Pre-commissioning/Start Up Authority
-
Is system ready for start up?
-
Is system ready for auto sequence enable?
-
Add signature
General Conditions, Photos, and Miscellaneous Notes
-