Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Mechanical Contractor
-
Is piping installed and layout checked?
-
Are hangers/piping supports properly installed and spaced?
-
Are valves properly located and installed?
-
Is heating water piping completed and tested to all equipment?
-
Is the make up water piping system complete and operational?
-
Is pressure relief valve installed and piped to a safe location?
-
Has piping been completed, tested, and inspected by City/Owner?
-
Is vibration isolation installed installed on piping and equipment?
-
Are all temperature control wells and valves installed?
-
Has all equipment utilizing heating water been checked?
-
Sufficient load for Boilers as required for complete start-up?
-
Are low point equipment drains installed?
-
Is chemical treatment installed and ready?
-
Is access for service provided?
-
Is unit installed per manufacturer instructions?
-
Is gas piping completed, tested, and inspected by city and owner?
-
Is gas pressure verified to be at listed inlet pressure on boiler?
-
Is gas pressure regulator vent piped to outside?
-
Has the manufacturer start up request sheet been completed?
-
Add signature
Electrical Contractor
-
Are power requirements for controls completed and turned on?
-
Is power available to disconnect/starter on boiler?
-
Is access to electrical clear and per NEC?
-
Is permanent lighting in place and powered on?
-
Add signature
Control Contractor
-
Is access to controls provided?
-
Has control contractor completed point to point check?
-
Are control panel terminations complete and is panel clean?
-
Add signature
Insulation Contractor
-
Is piping insulation complete per spec?
-
Add signature
Chemical Treatment Contractor
-
Are chemical feeder and glycol pump ready for use?
-
Are system chemicals onsite with MSDS sheets?
-
Add signature
QMS
-
Submitted Model #
-
Submitted Voltage
-
Has system check been completed?
-
Add signature
Commissioning Authority
-
Is system ready for start-up?
-
All must sign off before start-up.
-
Add signature
General Conditions, Photos and Misc Notes
-
Add media