Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Mechanical Contractor
-
Is piping installed and tested per spec's?
-
Are triple duty or balancing valves installed?
-
Are flex connectors installed on piping?
-
Are seismic Isolators installed?
-
Are suction diffusers installed as required?
-
Is differential pressure switch installed per detail, as required?
-
Are pressure gauges installed per detail?
-
Is access provided for servicing?
-
Are low point drains installed?
Electrical Contractor
-
Is proper voltage verified to disconnect/starter/VFD?
-
-
Is access to electrical clear and per NEC?
-
Is power completed from disconnect/starter/VFD to motor?
-
Are power requirements complete and verified for controls?
Control Contractor
-
Is access provided to control devices?
-
Has control contractor completed a point to point check?
-
Are control panel terminations complete and is panel clean?
Insulation Contractor
-
Is insulation complete on piping per spec?
QMS
-
What is the submitted model number?
-
What is the submitted voltage?
-
Has a systems check been performed?
Commissioning Authority
-
Is system ready for start-up?
-
All must be signed off before start-up.
General Conditions, Photos, and Misc Notes
-
Add media