Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Mechanical Contractor

  • Is unit installed per manufacturers instructions?

  • Are valves and gauges properly installed as required?

  • Is piping complete and tested?

  • Has piping been inspected by city/owner?

  • Are welds painted and marked?

  • Is piping insulated and labeled per spec?

  • Is the overall piping appearance acceptable?

  • Are frame bolts tightened per manufacturers spec's?

  • Are unions and flanges properly located for servicing?

  • Is PRV installed?

  • Has the cleaning and flushing plan been approved?

  • Add signature

  • Have seismic isolators been installed?

  • Have required drip legs and traps been installed?

  • Add signature

Control Contractor

  • Is access to control devices provided?

  • Has control contractor completed point to point checks?

  • Are control panel terminations complete and is panel clean?

  • Add signature

Electrical Contractor

  • Is power available to control panel?

  • Add signature

Insulation Contractor

  • Is insulation completed on piping as per spec?

  • Add signature

QMS

  • What is the submitted model number?

  • Has a systems check been performed?

  • Add signature

Commissioning Authority

  • Is system ready for start-up?

  • All must be signed off prior to start-up

  • Add signature

General Conditions, Photos, and Misc Notes

  • Add media

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.