Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Select date
-
Add location
-
Initial inspection
- approved
- rejected
- n/a
-
Follow up Inspection
Safety/housekeeping
-
Is everyone wearing all the required PPE
-
Is a hot work permit filled out
-
Is a dig permit filled out
-
Add media
Products
-
PVC
-
Copper or Ductile (waterline)
Before Work Starts
-
Reviewed IWP
-
Is IWP signed by all on site employees (crews)
-
Have you checked all on site materials against what was approved
-
Do you have install drawings?
Installation
-
Is piping installed per the coordination drawings?
-
Are site utilities connected to the DW system and have an 8" expansion
-
Do all joints on the piping have initials
-
4" pipe and greater have a slope of 1/8" fall per foot
-
3" pipe and smaller have a slope of 1/4" fall per foot
-
Is grease waste pipe have1" insulation
-
Is there a floor drain in the boiler room?
-
Provide 8" of squeegee below and above all piping in amenities
-
If in amenities provide an expansion connection in the thru slab installation
-
Tested for 2hrs @ 150 psi or 10' head
Storage/Protection
-
Is all un used piping capped
-
All stored materials organized kept neat
-
Add media
Required Testing
-
Received 95% compaction on soil testing
Misc
-
Add drawing
-
Add media
-
Add media
RK Signature
-
Add signature
Mortenson Signature
-
Add signature
Other witnesses
-
Add signature
-
Add signature
-
Have all "no" items been moved to the Quit log