Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Mechanical Contractor
-
Is piping installed and tested?
-
Is sump pit clean?
-
Is pump Anchored to base?
-
Are flex connectors installed on piping, as per spec?
-
Are isolation/check valves installed per details?
-
Is area around pump clean and clear of debris?
-
Has pump coupling been aligned, if required?
-
Has pump been lubricated?
-
Is access for service provided?
-
Has drain line valve been installed?
-
Are pressure gauges installed per detail?
-
Has pressure differential switch been installed as detailed and required?
-
Add signature
Electrical Contractor
-
Has proper voltage to disconnect/starter/VFD been verified?
-
Is access to electrical clear and per NEC?
-
Is power from disconnect/starter/VFD to motor completed?
-
Have power requirements for controls been completed and verified?
-
Add signature
Control Contractor
-
Has access to control devices been provided?
-
Has control contractor completed point to point check?
-
Are control panel terminations complete and is the panel clean?
-
Add signature
QMS
-
What is the submitted model number?
-
What is the submitted voltage?
-
Has a system check been performed?
-
Add signature
Commissioning Authority
-
Is system ready for start-up?
-
All must be signed-off prior to start-up.
-
Add signature
General Conditions, Photos, and Misc Notes
-
Add media