Title Page
-
Site conducted
-
Start date
-
End Date
-
Hours worked per day
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
-
Prepared by
-
Location
What H&S Checks have been completed
-
Risk assessment
-
Method Statement
-
Procedures
Which other Persons have you had contact with when gathering/providing information?
-
Cilent
-
What information did you need?
-
Architect
-
What information did you need?
-
Design engineer
-
What information did you need?
-
Quantity surveyor
-
What information did you need?
-
Clerk of works
-
What information did you need?
-
Structural engineer
-
What information did you need?
-
Estimator
-
What information did you need?
-
Project Manager
-
What information did you need?
-
Contracts manager
-
undefined
-
Sub contractor/ other trades
-
What information did you need?
-
Site supervisor/ supervisor
-
What information did you need?
What Technical information and functional information have you used LO 1.2
-
Job specifications
-
British standards
-
Codes of Practice
-
Manufacturers instructions
-
Reports/ critical path analysis
-
Site plans
-
Job sheets
-
Data sheets/ wall charts
-
Circuit/ wiring diagrams
-
Layout/ site drawings
-
Assembly/ detailed drawings
-
Variation order
-
Time sheets/ Day work sheets
-
Delivery notes
-
Other - please specify
Which trades have you had to communicate with during the work activities? LO 3.1/3.2/3.3/5.2/5.3
-
Brick layer
-
What information did you need?
-
What communication method was used?
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Joiner
-
What information did you need?
-
What communication method was used?
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Plasterer
-
What information did you need?
-
What communication method was used?
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Electrician
-
What information did you need?
-
What communication method was used?
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Tiler
-
What information did you need?
-
What communication method was used
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Engineer
-
What information did you need?
-
What communication method was used?
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Plumber
-
What information did you need?
-
What communication method was used?
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Decorator
-
What information did you need?
-
What communication method was used
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Ground worker
-
What information did you need?
-
What communication method was used
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
-
Other- please specify
-
What information did you need?
-
What communication method was used?
- Face to Face conversation
- Telephone conversation
- Text/ Social Media App
- Tool box Talk
- Drawings/ programmes and charts/ photos
- Job specification/ Work schedules
- Bulletins/ Notice boards
Trades onsite
-
Bricklayer
-
Joiner
-
Tiler
-
Plasterer
-
Electrician
-
Plumber
-
Decorator
-
Ground worker
-
HV fittter
-
Gas fitter
-
other
Electrical work programme, Please complete a electrical programme of works to demonstrate the planned work activities for a 5 day period. LO 6.1
-
Week beginning date
Day 1 A.M
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 1 P.M
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 2 A.M
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 2 P.M.
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 3 A.M.
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 3 P.M.
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 4 A.M.
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 4 P.M.
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 5 A.M.
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Day 5 P.M.
-
Task Description e.g Site induction
-
What Labour is Required e.g. 1 Supervisor 1 Electrician 1 Apprentice
-
What resources are required e.g PPE, Hand tools, Test kit, Step ladders, SWA cable
Supplementary evidence (two of the following)
-
Delivery note
-
Variation Order
-
Written Quotation
-
Material/ plant order documentation
Professional Discussion Questions (Assessor use only) P.D. Questions are optional and can be used to supplement this unit. Please tick which questions have been asked and upload evidence of recorded discussion
-
Can you describe how you planned and organised activities on this electrical job?
-
What safety checks did you complete before starting the work?
-
How did you communicate with other trades on-site?
-
What technical information did you need to complete this job?
-
Can you explain how you kept track of progress and recorded completed tasks?
-
What challenges did you face, and how did you resolve them?
-
How did you ensure that the correct tools and materials were available?
-
What would you do differently next time to improve your planning and oversight?
-
How did you ensure the work met industry standards and client expectations?
Declaration
-
By the act of making this submission I am declaring that this is all my own work and that: • The work has not, in whole or in part, been knowingly submitted elsewhere for assessment • Where the submission includes work from a previous assessment this has been identified • Where materials have been used from other sources it has been properly acknowledged • If this statement is untrue, I acknowledge that an assessment offence has been committed Attention is drawn to the plagiarism, collusion and cheating policies of both the centre and of the awarding body. Proven incidents of plagiarism, collusion or cheating can result in a student being withdrawn from a qualification. I confirm that I have read and understood the above statements on plagiarism and collusion. I confirm that I have not committed plagiarism when completing the work contained in this evidence, nor have I colluded with another student in the preparation and production of this work. I am satisfied with the way the learning activity/Assessment(s) was conducted and with the outcome(s). I agree that the information provided here is an accurate account of what has taken place
Expert witness Signature
-
As the expert witness I can confirm that all the work carried out in this unit has been done by the student named above under my supervision to the required standards.
Work Based Tutor Signature
-
I agree that the information provided here is an accurate account of what has taken place