Title Page

  • Location

  • Conducted on

  • Prepared by

Installation of RH25 Intumescent Strip

  • Is the Intumescent strip installed in accordance with manufactures details?

Installation of RV90/60 fire barriers

  • Have joints between lengths been tightly abutted?

  • Have joints between abutting lengths been taped using Siderise RFT?

  • Are Vertical fire barriers installed in accordance with construction issue drawings?

  • Are the Vertical fire barriers installed in accordance with the manufacturer’s details?

  • <br>Is there any compression on the fire barriers once the cladding has been reinstated?

Installation of Duo Slab Insulation

  • Is the cavity formed between the back of the panel and the face of the concrete floor slab suitable for Duo Slab installation?

Installation of Cladding

  • Are all items installed line and level?

  • Are all items free of defects?

Completion

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.