Information
-
Operator:
-
Rig Name:
-
Rig Activity:
-
Well #:
-
Commissioning Date:
-
Superintendent Name:
-
EDS Computer with all Operations and HSE Reports
-
Printer with extra paper and ink cartridges?
-
Retort Kit complete with Accessories
-
Risk Assessment/ JSA Completed
-
All Equipment Spotted As Per Survey
-
All Transfer Hoses Ran in a Safe Manner
-
All Pollution Pans in Place as Required
-
All Electrical Wires Ran in a Safe Manner
-
All Equipment Properly Grounded
-
ALL Fire Alarms / Vents in Living Quarters Properly Functioning<br>
-
ALL Fire Extinguishers / Strategically Located / Charged / Inspected<br>
-
Verify Safety Fall Device On Centrifuge Installed & Operational<br>
-
All Hazards Identified and Mitigated<br>
-
Centrifuge Stand Has All Support Pins In Place W/ Safety Pin Keepers<br>
-
Effluent Line Under Carriage of Centrifuge Secured<br>
-
Minimum / 1 Ea Case of HT Grease<br>
-
Centrifuge Pond Depth Set At 7 - 7.5<br>
-
Rig Shaker Screens API 200 - 230<br>
-
Take Pictures of Third Party Equip. - Excavator, Generator etc…<br>
-
All Information on DOR Regarding Co Rep Names & Contact Numbers<br>
-
All Information on DOR Regarding EDS Assets<br>
-
All Information on DOR Regarding Prices As Per Bid Sheet<br>
-
EDS Tool Box / Adequate w/ Hand Tools & Spare Parts<br>
-
Contingency Strategies In Place for Equipment To Avoid NPT<br>
-
Completed and attached a retort on Active System-prior to start-up/process<br>