Information
-
Document No. (Automatically generated, do not overwrite)
-
Site
-
Conducted on
-
Prepared by
-
Location
Design
-
Is the site working to the most up to date drawings?
-
Photo of drawing register.
-
Are there any further drawings required?
Quality Inspection
Substrate
-
Is the Substrate in Good Condition
-
Has the substrate been signed off by the project engineer
-
Are Additional works required to substrate - If so, please list and confirm Commercial have been notified
Carrier System
-
Have the carrier system brackets been installed as per Topek / Supplier Installation drawings at the correct centers
-
Are the correct Dead / Sliding Fix brackets in the correct locations as shown on Installation drawings
-
Have the correct Stainless steel fixings been used in accordance with Topek Details
-
Have the correct quantity of fixings been used in accordance with Topek details
-
Has the support rail been fixed to the Bracket using 2No. Stainless steel fasteners
Cavity Barriers
-
Have Cavity barrier brackets been installed using the correct quantity of fixings as per Topek Installation drawing IG002
-
Have brackets been installed using the correct type of Stainless Steel un-washered fixing
-
Have the cavity brackets been installed at the correct centers suited to the cavity barrier Length as per IG002
-
Has the Vertical cavity barrier been installed as to take precedence over the Horizontal
-
Have Non Vented vertical barriers been installed to ensure 5mm compression to back face of finished facade
-
Have Vented Horizontal barriers been installed with a minimum of 10mm Gap and maximum gap of 25mm (VFB) or 44mm (VFB Plus)
-
Are all Junctions of Cavity Barriers been installed tightly with no gaps
-
Has the manufacturer attended site and provided a report for each area of work
Insulation
-
Has the fixing layout been installed as per Installation Guide - IG003
-
Have the correct fasteners been used as per Topek details and IG003
-
Has the insulation been fixed in a brick bonded pattern with no gaps
Facade System
-
Has the facade system been installed as per Topek Layout drawings
-
Has the Specification and Colour been checked against construction drawings
-
Has the correct Stainless Steel fixings been used as noted described on Topek details
-
Has the fixing arrangement as noted on Topek details been checked
-
Have all fixings been installed within minimum edge distance requirements
Flashings
-
Have all flashings been installed as per Topek Installation Guidelines - IG004
-
Are all fixings used on Flashings stainless steel
-
Are all Flashings free of defect and the correct colour
-
Are all butt straps in place and lapped & fixed as per Topek details
Any Other findings
-
Insert any other significant findings
Sign Off
-
Auditor