  • Purpose of the document: To guide the members of the BAC, especially the presiding officer in planning and conducting a Pre-bid conference

  • Objective of the activity: To clarify and/or explain any of the requirements, terms, conditions, and specifications stipulated in the bidding documents (RIRR RA 9184, 32.1)

Bid Contract Information

  • Name of contract to be bid

  • Indicate the approved budget of the contract (ABC)

  • Time and date of the deadline of submission of bids

  • Time and date of the opening of bids.

  • Amount and validity of the bid security for each acceptable form.

Planning

  • The BAC, BAC Secretariat and BAC TWG have been informed of the schedule.

  • Invitations have been sent to the bidders that bought bidding documents and bidders that sent Letter of Intent.

  • The venue has been arranged. Attendance sheets and snacks (if available) have been arranged.

  • The bidding document is available for reference.

Implementation

  • Call the meeting to order. Have the BAC secretariat confirm that those in attendance have purchased the bid documents. Acknowledge the participants based on the attendance sheet.

  • Read out the eligibility requirements based on the bidding document.

  • Emphasize that the bidders must have a single contract within the stated number of years that is similar to the project to be bid and equivalent to at least 50% of the ABC.

  • Announce the required amount for the bid security and the validity of the bid security. Emphasize the required time for the validity of the bid and of the bid security.

  • Announce that blanks or the absence of a bid price in the schedule of requirements will disqualify the bid or cause it to be declared non-responsive.

  • Reiterate the provisions of RIRR RA 9184, 32.2.3

  • Are there questions from the participants?

  • Issues and concerns raised by the participants.

  • Issues and concerns for supplemental/bid bulletin

  • If the participants have no more questions or clarifications then declare adjournment.

Process Evaluation

  • Is the Pre-bid conference held at least twelve (12) calendar days before the deadline for submission and receipt of bids?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.